8736 N LEMONA AVE 91343
Certificate Information: 8736 N LEMONA AVE 91343
- Application / Permit
- 21014-10000-06227
- Plan Check / Job No.
- B21LA23375
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 800 SQFT ADU ATTACHED TO EXISTING SFD PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 6/28/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2022 | ADRIANA LOPEZ |
| Corrections Issued | 1/19/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 1/19/2022 | KEN GILL |
| Building Plans Picked Up | 1/25/2022 | APPLICANT |
| Applicant returned to address corrections | 5/19/2022 | ADRIANA LOPEZ |
| Plan Check Approved | 6/22/2022 | ADRIANA LOPEZ |
| Issued | 6/28/2022 | APPLICANT |
| CofO in Progress | 8/2/2023 | DAVID MATSON |
| Permit Finaled | 8/9/2023 | RUBEN SALAS |
| CofO Issued | 8/9/2023 | RUBEN SALAS |
| Permit Finaled | 8/9/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Stormwater Pollution Mitigatn | Cleared | 4/12/2022 | CHRIS VONG |
| Address approval | Cleared | 4/13/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 4/13/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/18/2022 | DAGOVERTO GUERRERO |
| Miscellaneous | Cleared | 5/20/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pachunuri,, Nalin Kumar; Lic. No.: C78970 | 21126 INGOMAR CT CANOGA PARK, CA 91304 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/9/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Rough-Elec/Plmb/HVAC | 2/9/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/24/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 3/29/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 3/30/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 3/30/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 3/30/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 3/30/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 3/30/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 3/30/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Wood Frame | 3/30/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 4/10/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 4/10/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 4/10/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 4/10/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 4/10/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Wood Frame | 4/10/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Gas Test | 4/14/2023 | Approved | MICHEL ABAJAN |
| Insulation | 4/14/2023 | Corrections Issued | MICHEL ABAJAN |
| Drywall Nailing | 4/21/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 4/21/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/21/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/1/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 5/1/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/30/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 6/30/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 6/30/2023 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 6/30/2023 | Approved | GREGG CUMMINGS |
| Gas Test | 6/30/2023 | Approved | GREGG CUMMINGS |
| Green Building Final | 6/30/2023 | Approved | GREGG CUMMINGS |
| HVAC-Final | 6/30/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 6/30/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 6/30/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 6/30/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 6/30/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 7/10/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 7/10/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 7/10/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 7/10/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 7/21/2023 | Approved | DAVID MATSON |
| Final | 7/21/2023 | OK to Issue CofO | DAVID MATSON |
| Service/Power Release | 7/21/2023 | Not Ready for Inspection | DAVID MATSON |