3018 S SOMERSET DR 90016

Certificate Information: 3018 S SOMERSET DR 90016

Application / Permit
21014-10000-06214
Plan Check / Job No.
B21LA23351
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT (E) DEATACHED 1-CAR GARAGE (220 SF) TO ADU AND ADD (223 SF) PER CA GC 65852.2(e)(1)(B) AND LAMC 12.22.A.33(c)-(d),(g).
Permit Issued
Issued on 5/17/2022
Issuing Office
Current Status
CofO Issued on 2/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2021 APPLICANT
Assigned to Plan Check Engineer 12/28/2021 VIVIAN LAO
Corrections Issued 12/29/2021 VIVIAN LAO
Applicant returned to address corrections 4/13/2022 VIVIAN LAO
Applicant returned to address corrections 4/29/2022 VIVIAN LAO
Plan Check Approved 5/4/2022 VIVIAN LAO
Issued 5/17/2022 MARIA V VASQUEZ
Issued 5/17/2022 APPLICANT
Issued 12/6/2022 APPLICANT
CofO in Progress 2/9/2024 STUART CHAPMAN
Permit Finaled 2/12/2024 DEROLD HAUFF
CofO Issued 2/12/2024 DEROLD HAUFF
Permit Finaled 2/12/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/16/2022 CINDY QI
Roof/Waste drainage to street Cleared 3/16/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 3/17/2022 CINDY QI
Sewer availability Cleared 3/17/2022 CINDY QI
Construction near power lines Cleared 3/21/2022 RIDWAN HARDY
Construction within easement Cleared 3/21/2022 RIDWAN HARDY

Contact Information

Architect Murnane,, R Mcshane; Lic. No.: C34176 2898 ROWENA AVENUE UNIT 102      LOS ANGELES, CA 90039
Contractor Owner-Builder       ,
Engineer Tan,, Charles; Lic. No.: NA4758       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/12/2022 Approved STUART CHAPMAN
Pre-Inspection 1/20/2023 Partial Inspection CALEB MEISTER
Excavation/Setback/Form/Re-Bar 1/24/2023 Corrections Issued CALEB MEISTER
Excavation/Setback/Form/Re-Bar 2/16/2023 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 2/16/2023 Partial Approval CALEB MEISTER
Footing/Foundation/Slab 3/7/2023 Not Ready for Inspection CALEB MEISTER
METHANE-Barrier 3/7/2023 Approved CALEB MEISTER
METHANE-Subgrade 3/7/2023 Approved CALEB MEISTER
PLUMBING-Rough 3/7/2023 Partial Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 Partial Approval CALEB MEISTER
ELECTRICAL-Rough 6/2/2023 Approved CALEB MEISTER
HVAC-Rough 6/2/2023 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 6/2/2023 Not Ready for Inspection CALEB MEISTER
Sewer 6/2/2023 Not Ready for Inspection CALEB MEISTER
Wood Frame 6/2/2023 Not Ready for Inspection CALEB MEISTER
HVAC-Rough 6/20/2023 Approved CALEB MEISTER
Insulation 6/20/2023 Corrections Issued CALEB MEISTER
PLUMBING-Rough 6/20/2023 Corrections Issued CALEB MEISTER
Wood Frame 6/20/2023 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 7/20/2023 Conditional Approval CALEB MEISTER
Green Building Rough 7/20/2023 Approved CALEB MEISTER
HVAC-Rough 7/20/2023 Approved CALEB MEISTER
Insulation 7/20/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 7/20/2023 Approved CALEB MEISTER
METHANE-Rough 7/20/2023 Approved CALEB MEISTER
PLUMBING-Rough 7/20/2023 Approved CALEB MEISTER
Wood Frame 7/20/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 8/23/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 8/31/2023 Approved CALEB MEISTER
Shower Pan 8/31/2023 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Final 10/30/2023 Not Ready for Inspection CALEB MEISTER
HVAC-Final 10/30/2023 Not Ready for Inspection CALEB MEISTER
PLUMBING-Final 10/30/2023 Not Ready for Inspection CALEB MEISTER
Drywall Nailing 1/12/2024 Approved STUART CHAPMAN
Final 1/12/2024 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 1/12/2024 Approved STUART CHAPMAN
Green Building Final 1/12/2024 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Approved STUART CHAPMAN
Smoke Detectors 1/12/2024 Approved STUART CHAPMAN
ELECTRICAL-Final 2/9/2024 Approved STUART CHAPMAN
Final 2/9/2024 OK to Issue CofO STUART CHAPMAN
HVAC-Final 2/9/2024 Approved STUART CHAPMAN
PLUMBING-Final 2/9/2024 Approved STUART CHAPMAN
Service/Power Release 2/9/2024 Approved STUART CHAPMAN