475 W CANYON VISTA DR 90065

Certificate Information: 475 W CANYON VISTA DR 90065

Application / Permit
21014-10000-06206
Plan Check / Job No.
B21LA23305
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ALTERATION OF (E) 2-STORY SINGLE FAMILY RESIDENCE AND 88 SF ADDITION
Permit Issued
Issued on 3/10/2022
Issuing Office
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 CRYSTEL MAALOUF
Corrections Issued 1/6/2022 CRYSTEL MAALOUF
Quality Review Completed 1/7/2022 SEAN DANG
Plan Check Approved 3/2/2022 CRYSTEL MAALOUF
Issued 3/10/2022 APPLICANT
Building Plans Picked Up 3/14/2022 APPLICANT
CofO in Progress 8/23/2024 OSVALDO PARAMO
CofO Issued 9/17/2024 DEROLD HAUFF
Permit Finaled 9/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 1/12/2022 NASHYA JENSEN
Sewer availability Cleared 2/9/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 2/14/2022 STEVE MELGAR
GPI Written Notices Cleared 3/2/2022 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 3/2/2022 CRYSTEL MAALOUF

Contact Information

Contractor Owner-Builder       ,
Engineer Faghihi,, Mahmoud; Lic. No.: S5789 888 S FIGUEROA ST 18TH FLOOR      LOS ANGELES, CA 90017

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/1/2022 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 7/29/2022 Approved OSVALDO PARAMO
Wood Frame 9/6/2022 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 9/9/2022 Not Ready for Inspection OSVALDO PARAMO
HVAC-Rough 9/9/2022 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 9/9/2022 Approved OSVALDO PARAMO
Wood Frame 9/9/2022 Not Ready for Inspection OSVALDO PARAMO
Wood Frame 9/19/2022 Not Ready for Inspection AMY COLIN
ELECTRICAL-Rough 9/26/2022 Approved OSVALDO PARAMO
HVAC-Rough 9/26/2022 Partial Inspection OSVALDO PARAMO
Wood Frame 9/26/2022 Not Ready for Inspection OSVALDO PARAMO
HVAC-Rough 9/30/2022 Approved OSVALDO PARAMO
Wood Frame 9/30/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 10/11/2022 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 10/11/2022 Not Ready for Inspection OSVALDO PARAMO
Service/Power Release 10/11/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 10/24/2022 Approved OSVALDO PARAMO
Green Building Rough 10/24/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 10/24/2022 Partial Approval OSVALDO PARAMO
Insulation 11/2/2022 Approved OSVALDO PARAMO
Drywall Nailing 11/7/2022 Approved OSVALDO PARAMO
Final 2/14/2023 Not Ready for Inspection OSVALDO PARAMO
Green Building Final 2/14/2023 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 2/14/2023 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 2/14/2023 Not Ready for Inspection OSVALDO PARAMO
Final 9/19/2023 Corrections Issued OSVALDO PARAMO
Smoke Detectors 9/19/2023 Approved OSVALDO PARAMO
Final 7/8/2024 Conditional Approval OSVALDO PARAMO
Final 8/19/2024 OK to Issue CofO OSVALDO PARAMO