849 N MEYLER ST 90731

Certificate Information: 849 N MEYLER ST 90731

Application / Permit
21014-10000-06187
Plan Check / Job No.
B21LA23257
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE-STORY GROUND FLOOR ADDITION TO THE REAR OF (E) SINGLE FAMILY DWELLING TO CREATE NEW PRIMARY BEDROOM AND BATHROOM AND COVERED PATIO. (NFPA 13D THROUGOUT)
Permit Issued
Issued on 5/6/2022
Issuing Office
Current Status
Issued on 5/6/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/13/2021 APPLICANT
Assigned to Plan Check Engineer 12/15/2021 MINA HABILI
Corrections Issued 12/17/2021 MINA HABILI
Applicant returned to address corrections 2/8/2022 GEORGE ALVAREZ
Applicant returned to address corrections 4/23/2022 GEORGE ALVAREZ
Plan Check Approved 4/26/2022 GEORGE ALVAREZ
Issued 5/6/2022 APPLICANT
Building Plans Picked Up 5/10/2022 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/11/2022 ERIK BEASLEY
BHO/Hillside ordinance Cleared 1/11/2022 ERIK BEASLEY
BHO/Hillside ordinance Cleared 1/11/2022 ERIK BEASLEY
BHO/Hillside ordinance Cleared 1/11/2022 ERIK BEASLEY
BHO/Hillside ordinance Cleared 1/11/2022 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 1/11/2022 ERIK BEASLEY
Sewer availability Cleared 1/11/2022 ERIK BEASLEY
Grading Pre-Inspection Cleared 1/13/2022 MATTHEW JENKINS
Low Impact Development Cleared 4/14/2022 SUNG JOON WON
GPI Written Notices Cleared 4/15/2022 CHRISTOPHER KOMANCHECK
Roof/Waste drainage to street Cleared 4/15/2022 JOSE HERNANDEZ

Contact Information

Architect Relatores,, Rand Denina; Lic. No.: C24070 4010 PALOS VERDES DRIVE N # 200D      ROLLING HILLS ESTATES, CA 90274
Contractor Owner-Builder       ,
Engineer Baluyut,, Agustin Pangilinan; Lic. No.: C66025 22828 S CYPRESS DR      CARSON, CA 90745

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/3/2022 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 8/19/2022 Partial Approval EUGENE CASSIDY
Green Building Rough 8/19/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 8/19/2022 Partial Approval EUGENE CASSIDY
Verify Sprinkler Sign Off 8/19/2022 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 8/25/2022 Partial Approval ANSON MAGLASANG
Green Building Rough 8/25/2022 Not Ready for Inspection ANSON MAGLASANG
Verify Sprinkler Sign Off 8/25/2022 Not Ready for Inspection ANSON MAGLASANG
BUILDING-Rough-Frame 9/29/2022 Partial Approval EUGENE CASSIDY
Green Building Rough 9/29/2022 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 9/29/2022 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/26/2022 Partial Approval ANSON MAGLASANG
PLUMBING-Rough 10/26/2022 Approved ANSON MAGLASANG
Interior/Exterior Lathing 12/12/2022 Approved JAMES CHAVEZ
Shower Pan 12/12/2022 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 2/14/2023 Approved JOHN KLARIN
Green Building Rough 2/14/2023 Approved JOHN KLARIN
Verify Sprinkler Sign Off 2/14/2023 Approved JOHN KLARIN
Insulation 3/7/2023 Approved EUGENE CASSIDY
Drywall Nailing 4/7/2023 Approved ANSON MAGLASANG
Interior/Exterior Lathing 4/19/2023 Approved JAMES CHAVEZ