14260 W FILMORE ST 91331

Certificate Information: 14260 W FILMORE ST 91331

Application / Permit
21014-10000-06171
Plan Check / Job No.
B21LA23210
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SECOND STORY ADDITION TO (E) 2-STORY SFD
Permit Issued
Issued on 5/20/2022
Issuing Office
Valley
Current Status
Issued on 5/20/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/28/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 KHEDER ALRAZAA
Corrections Issued 2/17/2022 KHEDER ALRAZAA
Quality Review Completed 2/24/2022 KEN GILL
Building Plans Picked Up 3/2/2022 APPLICANT
Plan Check Approved 4/18/2022 KHEDER ALRAZAA
Issued 5/20/2022 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/23/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 3/29/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 3/29/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/15/2022 Corrections Issued JENNIFER RABUCHIN
METHANE-Barrier 7/15/2022 Approved JENNIFER RABUCHIN
METHANE-Subgrade 7/15/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/27/2022 Not Ready for Inspection JENNIFER RABUCHIN
Drywall Nailing 7/27/2022 Not Ready for Inspection JENNIFER RABUCHIN
Final 7/27/2022 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 7/27/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 7/27/2022 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 7/27/2022 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Final 7/27/2022 Approved JENNIFER RABUCHIN
METHANE-Rough 7/27/2022 Approved JENNIFER RABUCHIN
Pre-Inspection 7/27/2022 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/27/2022 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 7/27/2022 Not Ready for Inspection JENNIFER RABUCHIN
Deputy Other (see comments) 7/28/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 8/5/2022 Approved JENNIFER RABUCHIN
Deputy Reinf. Concrete 8/11/2022 Partial Approval JENNIFER RABUCHIN
Special/Order Compliance 8/16/2022 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/2/2022 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/2/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 9/2/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 10/12/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 10/12/2022 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/15/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 11/15/2022 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Partial Approval JENNIFER RABUCHIN
Green Building Rough 11/15/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/15/2022 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/15/2022 SGSOV Approved JENNIFER RABUCHIN
Drywall Nailing 12/14/2022 Not Ready for Inspection ROBERT GOLD
Green Building Rough 12/14/2022 Not Ready for Inspection ROBERT GOLD