3151 N GLENMANOR PL 90039
Certificate Information: 3151 N GLENMANOR PL 90039
- Application / Permit
- 21014-10000-06168
- Plan Check / Job No.
- B21LA23201
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF (E) SFD. PATIO COVER ( 8'-4" x 18'-0") ADDITION ON 1ST FLOOR WITH NEW ROOFTOP DECK ON TOP ON THE 2ND FLOOR.
- Permit Issued
- Issued on 2/10/2022
- Issuing Office
- Current Status
- CofO Issued on 8/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 12/29/2021 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 12/30/2021 | SAI KHUM |
| Plan Check Approved | 1/27/2022 | FARSHAD ALIMOHAMADI |
| Issued | 2/10/2022 | APPLICANT |
| Building Plans Picked Up | 2/15/2022 | APPLICANT |
| CofO in Progress | 8/22/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 8/26/2022 | DEROLD HAUFF |
| CofO Issued | 8/26/2022 | DEROLD HAUFF |
| Permit Finaled | 8/26/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/7/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/23/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/1/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/22/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Wood Frame | 5/3/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/10/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 5/10/2022 | Approved | HAMIK HARTOUNIAN |
| Rough-Elec/Plmb/HVAC | 5/10/2022 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 5/10/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 5/17/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Drywall Nailing | 5/18/2022 | Approved | HAMIK HARTOUNIAN |
| Gas Test | 6/15/2022 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 6/22/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 8/1/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/1/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/1/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 8/5/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 8/22/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |