4143 S CLOVERDALE AVE 90008
Certificate Information: 4143 S CLOVERDALE AVE 90008
- Application / Permit
- 21014-10000-06135
- Plan Check / Job No.
- B21LA23111
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND STORY ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 7/7/2023
- Issuing Office
- Current Status
- Issued on 7/7/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2021 | DANIEL YIP |
| Corrections Issued | 1/6/2022 | DANIEL YIP |
| Quality Review Completed | 1/12/2022 | KEN GILL |
| Plan Check Approved | 8/23/2022 | DANIEL YIP |
| Issued | 7/7/2023 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/29/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2022 | CINDY QI |
| Sewer availability | Cleared | 3/31/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 5/7/2022 | KURT CORRAL |
| GPI Written Notices | Cleared | 8/23/2022 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 8/23/2022 | DANIEL YIP |
Contact Information
| Contractor | J J C Construction Inc; Lic. No.: 1075265-B | 2307 W 78TH PLACE INGLEWOOD, CA 90305 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/27/2023 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 9/11/2023 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 9/14/2023 | Partial Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 9/29/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 10/13/2023 | Partial Inspection | ANTHONY EGSON |
| METHANE-Barrier | 10/13/2023 | Not Ready for Inspection | ANTHONY EGSON |
| METHANE-Subgrade | 10/13/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 11/1/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/11/2023 | Corrections Issued | ANTHONY EGSON |
| METHANE-Barrier | 12/11/2023 | Approved | ANTHONY EGSON |
| METHANE-Subgrade | 12/11/2023 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/14/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 1/18/2024 | Not Ready for Inspection | ANTHONY EGSON |
| METHANE-Rough | 1/18/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Deputy Wood Construction | 1/19/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 3/27/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Gas Test | 3/27/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 3/27/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 3/27/2024 | Approved | ANTHONY EGSON |
| Structural Steel Frame | 3/27/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/2/2024 | Approved | ANTHONY EGSON |
| HVAC-Rough | 4/2/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/3/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 4/3/2024 | Not Ready for Inspection | ANTHONY EGSON |
| METHANE-Rough | 4/3/2024 | Approved | ANTHONY EGSON |
| Structural Steel Frame | 4/3/2024 | Partial Approval | ANTHONY EGSON |
| Sewer | 4/5/2024 | Approved | ANTHONY EGSON |
| Underground Mechanical | 4/8/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/13/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 5/13/2024 | Approved | ANTHONY EGSON |
| Underground Mechanical | 5/13/2024 | Approved | ANTHONY EGSON |
| Wood Frame | 5/13/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 5/15/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/15/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 5/20/2024 | Approved | JOSH MEISTER |
| Shower Pan | 5/31/2024 | Partial Approval | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/7/2024 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/11/2024 | Approved | ANTHONY EGSON |
| Sewer | 6/17/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/13/2024 | Approved | ANTHONY EGSON |
| Deck | 8/13/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 8/13/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 8/13/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 8/13/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 8/13/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 8/13/2024 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 8/13/2024 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 8/13/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 8/27/2024 | Approved | ANTHONY EGSON |
| Structural Steel Frame | 8/27/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 9/5/2024 | Approved | ANTHONY EGSON |
| HVAC-Final | 9/5/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 9/12/2024 | Approved | ANTHONY EGSON |
| Final | 10/17/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 10/17/2024 | Not Ready for Inspection | ANTHONY EGSON |