4423 W 62ND ST 90043

Certificate Information: 4423 W 62ND ST 90043

Application / Permit
21014-10000-06131
Plan Check / Job No.
B21LA23088
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: (N) 1ST AND 2ND STORY ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 5/6/2022
Issuing Office
Current Status
CofO Issued on 7/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2021 APPLICANT
Assigned to Plan Check Engineer 1/6/2022 DANIEL YIP
Corrections Issued 1/10/2022 DANIEL YIP
Quality Review Completed 1/11/2022 LIPING TENG
Applicant returned to address corrections 2/23/2022 DANIEL YIP
Plan Check Approved 5/5/2022 DANIEL YIP
Issued 5/6/2022 APPLICANT
CofO in Progress 7/16/2024 JOSE MACIAS
Permit Finaled 7/24/2024 DEROLD HAUFF
CofO Issued 7/24/2024 DEROLD HAUFF
Permit Finaled 7/24/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/13/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 1/19/2022 WALLIE JONG
Sewer availability Cleared 2/2/2022 WALLIE JONG
Grading Pre-Inspection Cleared 2/10/2022 ROBERT HUGHES
Low Impact Development Cleared 4/4/2022 CHRIS VONG

Contact Information

Contractor Carolina Nazario; Lic. No.: 1072428-B 2209 MICHIGAN AVE APT 210      LOS ANGELES, CA 90033

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/14/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 6/17/2022 Partial Approval HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 7/2/2022 Approved ENRIQUE MIRELES
Underground Mechanical 7/11/2022 No Access for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 7/14/2022 Approved ENRIQUE MIRELES
Service/Power Release 7/28/2022 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/1/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/9/2022 SGSOV Not Ready ENRIQUE MIRELES
Wood Frame 8/22/2022 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/13/2023 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Approved MICHAEL LEWIS
Reinforced Concrete Frame 4/25/2023 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 5/5/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 5/12/2023 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 5/17/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 5/17/2023 Approved ENRIQUE MIRELES
Deputy Wood Construction 5/19/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 6/2/2023 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 6/8/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 7/10/2023 Approved ENRIQUE MIRELES
Shower Pan 7/10/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 7/14/2023 Approved ENRIQUE MIRELES
HVAC-Rough 7/14/2023 Approved ENRIQUE MIRELES
Insulation 7/14/2023 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 7/14/2023 Approved ENRIQUE MIRELES
Insulation 7/31/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 7/31/2023 Approved ENRIQUE MIRELES
Drywall Nailing 8/4/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 8/23/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/18/2023 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 12/21/2023 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 12/27/2023 Partial Inspection DAVID FEILER
Service/Power Release 1/2/2024 Approved DAVID FEILER
Deck 3/11/2024 Corrections Issued JOSE MACIAS
Deck 3/15/2024 Corrections Issued JOSE MACIAS
ELECTRICAL-Final 4/11/2024 Corrections Issued JOSE MACIAS
Final 4/11/2024 Corrections Issued JOSE MACIAS
HVAC-Final 4/11/2024 Approved JOSE MACIAS
PLUMBING-Final 4/11/2024 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 4/11/2024 SGSOV Approved JOSE MACIAS
Smoke Detectors 4/11/2024 Corrections Issued JOSE MACIAS
ELECTRICAL-Final 5/3/2024 Approved SABAS ALONSO
Final 5/3/2024 Corrections Issued SABAS ALONSO
HVAC-Final 5/3/2024 Approved SABAS ALONSO
PLUMBING-Final 5/3/2024 Approved SABAS ALONSO
Smoke Detectors 5/3/2024 Approved SABAS ALONSO
Final 7/11/2024 OK to Issue CofO JOSE MACIAS