680 E 36TH ST 90011

Certificate Information: 680 E 36TH ST 90011

Application / Permit
21014-10000-06122
Plan Check / Job No.
B21LA23061
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF GARAGE INTO A.D.U. AND EXTEND A.D.U. PER STATE LAW.
Permit Issued
Issued on 6/20/2024
Issuing Office
Metro
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 LAWRENCE QUIRANTE
Corrections Issued 12/26/2021 LAWRENCE QUIRANTE
Building Plans Picked Up 1/6/2022 APPLICANT
Applicant returned to address corrections 9/1/2022 LAWRENCE QUIRANTE
Applicant returned to address corrections 1/22/2024 NEHEMIAS RAMOS
Plan Check Approved 2/2/2024 NGHI SU
Issued 6/20/2024 APPLICANT
CofO in Progress 1/28/2026 ALEJANDRO DE ARTOLA
Permit Finaled 1/28/2026 DEROLD HAUFF
CofO Issued 1/28/2026 DEROLD HAUFF
Permit Finaled 1/28/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/16/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 3/16/2022 JEANETTE VONG
Low Impact Development Cleared 2/14/2023 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 1/30/2024 DAVID LOPEZ
Sewer availability Cleared 1/30/2024 DAVID LOPEZ

Contact Information

Contractor New World Remodeling; Lic. No.: 877349-B 7731 ANGELS CT      FONTANA, CA 92336
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/10/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 9/10/2024 Corrections Issued CRAIG DAVIS
Footing/Foundation/Slab 10/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 10/11/2024 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/23/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/7/2025 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 1/7/2025 Approved ENRIQUE MIRELES
Green Building Rough 1/7/2025 Approved ENRIQUE MIRELES
HVAC-Rough 1/7/2025 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/7/2025 Approved ENRIQUE MIRELES
Insulation 1/10/2025 Approved JOHN QUINTANILLA
Drywall Nailing 1/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 1/22/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/3/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/3/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 4/3/2025 Approved ALEJANDRO DE ARTOLA
Green Building Final 4/3/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/3/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 4/3/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 4/3/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/21/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/21/2025 Approved ALEJANDRO DE ARTOLA
Final 8/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 8/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 8/21/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/21/2025 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 8/21/2025 Approved ALEJANDRO DE ARTOLA
Final 11/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 11/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 11/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 11/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 1/27/2026 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 1/27/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 1/27/2026 Approved ALEJANDRO DE ARTOLA