919 S HIGHLAND AVE 90036
Certificate Information: 919 S HIGHLAND AVE 90036
- Application / Permit
- 21014-10000-06115
- Plan Check / Job No.
- B21LA23049
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- STORAGE ADDITION TO (E) DETACHED GARAGE AND TO CONVERT PORTION OF (E) GARAGE IN TO LAUNDRY ROOM
- Permit Issued
- Issued on 3/21/2022
- Issuing Office
- Current Status
- Issued on 3/21/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2021 | RICARDO RAMIREZ |
| Corrections Issued | 12/16/2021 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 2/9/2022 | JOSEPH RAFOLS |
| Building Plans Picked Up | 2/9/2022 | APPLICANT |
| Plan Check Approved | 3/19/2022 | FERNANDO FLORES |
| Issued | 3/21/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 1/6/2022 | JEANETTE VONG |
| Construction near power lines | Cleared | 3/4/2022 | TINA MIRANDA |
Contact Information
| Architect | Yoo,, Won Warren; Lic. No.: C37091 | 2540 EVELYN STREET MONTROSE, CA 91020 |
| Contractor | Ho Yong Hoe; Lic. No.: 1017522-B | 4619 ROSEWOOD AVE APT #204 LOS ANGELES, CA 90004 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 5/5/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 5/5/2022 | Partial Approval | ARTHUR SARGSYAN |
| Insulation | 5/5/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Barrier | 5/5/2022 | Approved | ARTHUR SARGSYAN |
| METHANE-Subgrade | 5/5/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 5/5/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Pre-Inspection | 5/5/2022 | Approved | ARTHUR SARGSYAN |
| Reinforced Concrete Frame | 5/5/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 5/25/2022 | Not Ready for Inspection | ADAM ESCOTO |
| ELECTRICAL-Rough | 5/25/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Final | 5/25/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Footing/Foundation/Slab | 5/25/2022 | Corrections Issued | ADAM ESCOTO |
| Insulation | 5/25/2022 | Not Ready for Inspection | ADAM ESCOTO |
| PLUMBING-Final | 5/25/2022 | Not Ready for Inspection | ADAM ESCOTO |
| PLUMBING-Rough | 5/25/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Pre-Inspection | 5/25/2022 | Not Ready for Inspection | ADAM ESCOTO |