1442 E MONTECITO DR 90031
Certificate Information: 1442 E MONTECITO DR 90031
- Application / Permit
- 21014-10000-06064
- Plan Check / Job No.
- B21LA22836
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL AND ADDITION TO (E) ONE STORY SFD. COMPLETELY REROOF (E) 1-STORY SFD PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 3/17/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | TSE MING HUANG |
| Corrections Issued | 12/9/2021 | TSE MING HUANG |
| Building Plans Picked Up | 12/15/2021 | APPLICANT |
| Applicant returned to address corrections | 9/2/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 12/14/2022 | VICTOR CHEN |
| Applicant returned to address corrections | 2/10/2023 | DANIEL SMILEY |
| Plan Check Approved | 3/10/2023 | DANIEL SMILEY |
| Issued | 3/17/2023 | APPLICANT |
| CofO in Progress | 3/18/2024 | LILIANA PORTILLO |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
| CofO Issued | 3/29/2024 | DEROLD HAUFF |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/19/2022 | KIRK LINKLATER |
| "D" conditions | Cleared | 9/22/2022 | ANACANY HURTADO |
| "Q" conditions | Cleared | 9/22/2022 | ANACANY HURTADO |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 10/3/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 10/3/2022 | JEANETTE VONG |
Contact Information
| Contractor | Urquia Marvin; Lic. No.: 1064984-B | 11146 VAN BUREN AVE LOS ANGELES, CA 90044 |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/28/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 5/5/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 5/10/2023 | Partial Approval | AMY COLIN |
| ELECTRICAL-Rough | 9/27/2023 | Corrections Issued | AMY COLIN |
| HVAC-Rough | 9/27/2023 | Corrections Issued | AMY COLIN |
| PLUMBING-Rough | 9/27/2023 | Corrections Issued | AMY COLIN |
| Wood Frame | 9/27/2023 | Corrections Issued | AMY COLIN |
| Deputy Wood Construction | 9/28/2023 | Conditional Approval | AMY COLIN |
| ELECTRICAL-Rough | 10/2/2023 | Approved | AMY COLIN |
| HVAC-Rough | 10/2/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 10/2/2023 | Approved | AMY COLIN |
| Pre-Inspection | 10/2/2023 | Approved | AMY COLIN |
| Wood Frame | 10/2/2023 | Approved | AMY COLIN |
| Insulation | 10/17/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 10/17/2023 | Approved | AMY COLIN |
| Shower Pan | 10/17/2023 | Approved | AMY COLIN |
| Drywall Nailing | 12/29/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 3/1/2024 | Approved | LILIANA PORTILLO |
| Final | 3/1/2024 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 3/1/2024 | Approved | LILIANA PORTILLO |
| Green Building Rough | 3/1/2024 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 3/1/2024 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 3/1/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 3/15/2024 | Approved | LILIANA PORTILLO |
| Final | 3/15/2024 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 3/15/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 3/15/2024 | Approved | LILIANA PORTILLO |