1037 W 73RD ST 90044
Certificate Information: 1037 W 73RD ST 90044
- Application / Permit
- 21014-10000-06059
- Plan Check / Job No.
- B21LA22822
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1 STORY ADDITION TO (E) SFD, ALL WORK PER WFPP.
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- CofO Issued on 1/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2021 | DANIEL SANJUAN |
| Corrections Issued | 12/16/2021 | DANIEL SANJUAN |
| Plan Check Approved | 2/9/2022 | ADAM HEGAZI |
| Issued | 3/17/2022 | APPLICANT |
| Building Plans Picked Up | 3/23/2022 | APPLICANT |
| CofO in Progress | 1/8/2024 | MICHAEL LEWIS |
| CofO Issued | 1/10/2024 | DEROLD HAUFF |
| Permit Finaled | 1/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/8/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/6/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 5/4/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/9/2022 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 5/9/2022 | Partial Approval | LILIANA PORTILLO |
| Insulation | 5/13/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2022 | Corrections Issued | LILIANA PORTILLO |
| Pre-Inspection | 1/25/2023 | Partial Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 3/30/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/10/2023 | No Access for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 4/10/2023 | No Access for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/11/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 4/11/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 4/27/2023 | Corrections Issued | MICHAEL LEWIS |
| Interior/Exterior Lathing | 5/15/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 5/26/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 6/12/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 6/12/2023 | Approved | STUART CHAPMAN |
| Insulation | 6/14/2023 | Conditional Approval | MICHAEL LEWIS |
| Drywall Nailing | 6/22/2023 | Approved | STUART CHAPMAN |
| Insulation | 6/22/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/11/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 7/20/2023 | Approved | MICHAEL LEWIS |
| Final | 11/14/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 11/14/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 11/14/2023 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 11/14/2023 | Approved | MICHAEL LEWIS |
| Final | 1/5/2024 | OK to Issue CofO | MICHAEL LEWIS |