5014 S HARVARD BLVD 90062

Certificate Information: 5014 S HARVARD BLVD 90062

Application / Permit
21014-10000-06044
Plan Check / Job No.
B21LA22715
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE INTO ADU PER LAMC 12.22 A. 33 (c)-(d) 1ST & 2ND STORY ADDITION FOR NEW ADU WITH ATTACHED TRELLIS 12'X16'3''
Permit Issued
Issued on 11/30/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 SERGIO GUTIERREZ
Corrections Issued 1/10/2022 SERGIO GUTIERREZ
Quality Review Completed 1/13/2022 FARUK SEZER
Building Plans Picked Up 4/28/2022 APPLICANT
Applicant returned to address corrections 11/22/2022 SERGIO GUTIERREZ
Plan Check Approved 11/30/2022 SERGIO GUTIERREZ
Issued 11/30/2022 APPLICANT
CofO in Progress 4/15/2025 WAYNE REGESTER
Permit Finaled 4/20/2025 DEROLD HAUFF
CofO Issued 4/20/2025 DEROLD HAUFF
Permit Finaled 4/20/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/25/2022 STEVE MELGAR
Permit Cleared 5/25/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/8/2022 STEVE MELGAR
Sewer availability Cleared 6/8/2022 STEVE MELGAR
Construction within easement Cleared 9/28/2022 RIDWAN HARDY
Low Impact Development Cleared 10/24/2022 MARCO SANCHEZ
Hydrant and Access approval Cleared 10/25/2022 RUEL COLE
Roof/Waste drainage to street Cleared 10/25/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/15/2023 Conditional Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 5/19/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 5/19/2023 Approved MICHAEL LEWIS
Underground Mechanical 5/19/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 6/29/2023 Partial Approval SABAS ALONSO
Green Building Rough 6/29/2023 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 7/6/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Approved SABAS ALONSO
HVAC-Rough 7/6/2023 Approved SABAS ALONSO
PLUMBING-Rough 7/6/2023 Approved SABAS ALONSO
Underground Mechanical 7/6/2023 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 8/8/2023 Not Ready for Inspection CHARLES BOGHOSKHAN
Green Building Rough 8/8/2023 Approved CHARLES BOGHOSKHAN
Wood Frame 8/8/2023 Not Ready for Inspection CHARLES BOGHOSKHAN
BUILDING-Rough-Frame 8/11/2023 Corrections Issued SABAS ALONSO
Green Building Rough 8/11/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 8/21/2023 Approved SABAS ALONSO
Wood Frame 8/21/2023 Not Ready for Inspection SABAS ALONSO
Insulation 8/30/2023 Corrections Issued SABAS ALONSO
Insulation 9/6/2023 Approved JOSH MEISTER
Interior/Exterior Lathing 9/6/2023 Not Ready for Inspection JOSH MEISTER
Drywall Nailing 9/13/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 9/13/2023 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 9/27/2023 Partial Approval RONNIE MINDANAO
Interior/Exterior Lathing 9/29/2023 Approved RONNIE MINDANAO
Shower Pan 9/29/2023 Approved RONNIE MINDANAO
Final 3/28/2025 Not Ready for Inspection BARRY HACHE
Green Building Final 3/28/2025 Not Ready for Inspection BARRY HACHE
HVAC-Final 3/28/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Final 3/28/2025 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 3/28/2025 SGSOV Not Ready BARRY HACHE
Smoke Detectors 3/28/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 4/3/2025 Not Ready for Inspection BARRY HACHE
Final 4/3/2025 Not Ready for Inspection BARRY HACHE
Green Building Final 4/3/2025 Approved BARRY HACHE
HVAC-Final 4/3/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 4/3/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Not Ready BARRY HACHE
Smoke Detectors 4/3/2025 Approved BARRY HACHE
ELECTRICAL-Final 4/7/2025 Approved BARRY HACHE
HVAC-Final 4/7/2025 Approved BARRY HACHE
PLUMBING-Final 4/7/2025 Approved BARRY HACHE
Final 4/14/2025 OK to Issue CofO WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 4/14/2025 SGSOV Approved WAYNE REGESTER