4944-4948 N GLACIER DR 90041

Certificate Information: 4944-4948 N GLACIER DR 90041

Application / Permit
21014-10000-06023
Plan Check / Job No.
B21LA22613
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
RENOVATION AND 2-STORY ADDITION. RENOVATION AND RECONFIGURATION OF 4946 GLACIER. ADDITION OF AN ATTACHED ADU, 2 BED + 2 BATH PER ORDINANCE.
Permit Issued
Issued on 6/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 6/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 MICHAEL LOPEZ
Corrections Issued 1/13/2022 MICHAEL LOPEZ
Quality Review Completed 1/19/2022 KEN GILL
Building Plans Picked Up 1/24/2022 APPLICANT
Applicant returned to address corrections 5/5/2022 ARSALAN SHABESTARI
Plan Check Approved 5/18/2022 ARSALAN SHABESTARI
Issued 6/28/2022 APPLICANT
CofO in Progress 3/1/2024 CRAIG VAUGHAN
Permit Finaled 6/3/2024 DEROLD HAUFF
CofO Issued 6/3/2024 DEROLD HAUFF
Permit Finaled 6/3/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/26/2022 JEANETTE VONG
Sewer availability Cleared 2/26/2022 JEANETTE VONG
Address approval Cleared 3/3/2022 JEANETTE VONG
Hydrant and Access approval Cleared 3/28/2022 DWIGHT SANKEY
Low Impact Development Cleared 4/14/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 4/15/2022 CHRISTOPHER ROCHA
GPI Written Notices Cleared 5/5/2022 MICHAEL LOPEZ
Grading Pre-Inspection Cleared 5/5/2022 MICHAEL LOPEZ

Contact Information

Contractor Titan Construction; Lic. No.: 959142-B 9828 AMANITA AVE      TUJUNGA, CA 91042

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/1/2022 Partial Inspection AMY COLIN
PLUMBING-Rough 9/15/2022 Partial Approval AMY COLIN
Underground Mechanical 9/20/2022 Approved CRAIG VAUGHAN
Deputy Drilled-In Anchors 9/27/2022 Conditional Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 9/29/2022 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 9/29/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 10/28/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 10/28/2022 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 12/8/2022 Partial Approval CRAIG VAUGHAN
Wood Frame 12/8/2022 Partial Approval CRAIG VAUGHAN
Wood Frame 12/27/2022 Partial Inspection AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Corrections Issued SCOTT FINNILA
Wood Frame 2/9/2023 Partial Approval CRAIG VAUGHAN
Deputy Wood Construction 2/10/2023 Conditional Approval CRAIG VAUGHAN
Deputy Wood Construction 2/15/2023 Conditional Approval CRAIG VAUGHAN
Deputy Wood Construction 2/24/2023 Conditional Approval BRENDAN MORELLI
Deputy Wood Construction 3/2/2023 Conditional Approval AMY COLIN
HVAC-Rough 3/6/2023 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 3/20/2023 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 3/20/2023 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 3/20/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 4/5/2023 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Partial Approval CRAIG VAUGHAN
Shower Pan 4/11/2023 Approved ALIZAH MAYAGOITIA
Wood Frame 4/11/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/3/2023 Partial Approval JOAQUIN GREENOUGH
Insulation 5/15/2023 Approved BRIAN SULLIVAN
Drywall Nailing 5/22/2023 Not Ready for Inspection CRAIG VAUGHAN
Drywall Nailing 6/1/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 6/1/2023 Approved CRAIG VAUGHAN
Drywall Nailing 6/2/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 6/2/2023 Approved CRAIG VAUGHAN
Deputy Steel/Welding 7/14/2023 Approved CRAIG VAUGHAN
Service/Power Release 7/26/2023 Approved CRAIG VAUGHAN
Pre-Inspection 8/18/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Final 10/18/2023 Corrections Issued CRAIG VAUGHAN
HVAC-Final 10/18/2023 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 10/18/2023 Corrections Issued CRAIG VAUGHAN
HVAC-Final 11/15/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 11/15/2023 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 12/4/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Final 12/4/2023 Approved CRAIG VAUGHAN
Final 12/4/2023 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 12/4/2023 Approved CRAIG VAUGHAN
Gas Test 12/4/2023 Approved CRAIG VAUGHAN
Green Building Final 12/4/2023 Approved CRAIG VAUGHAN
Green Building Rough 12/4/2023 Approved CRAIG VAUGHAN
HVAC-Final 12/4/2023 Approved CRAIG VAUGHAN
MERV13>=Final 12/4/2023 Approved CRAIG VAUGHAN
MERV13>=Rough 12/4/2023 Approved CRAIG VAUGHAN
PLUMBING-Final 12/4/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 12/4/2023 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 12/4/2023 Approved CRAIG VAUGHAN
Final 12/13/2023 Corrections Issued CRAIG VAUGHAN
Final 2/1/2024 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 2/1/2024 Approved CRAIG VAUGHAN
Final 2/15/2024 No Access for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 2/15/2024 No Access for Inspection ALIZAH MAYAGOITIA
Final 2/20/2024 Corrections Issued CRAIG VAUGHAN
Final 2/29/2024 OK to Issue CofO CRAIG VAUGHAN