3423-3423 1/2 E 5TH ST 90063

Certificate Information: 3423-3423 1/2 E 5TH ST 90063

Application / Permit
21014-10000-06020
Plan Check / Job No.
B21LA22543
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan Conversion of existing attached garage to an accessory dwelling unit per Ordinance.
Permit Issued
Issued on 7/13/2022
Issuing Office
Current Status
CofO Issued on 9/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2021 APPLICANT
Assigned to Plan Check Engineer 12/27/2021 MONICA RAMIREZ
Corrections Issued 12/28/2021 MONICA RAMIREZ
Quality Review Completed 12/31/2021 PRANITA SHAH
Applicant returned to address corrections 1/31/2022 MONICA RAMIREZ
Applicant returned to address corrections 3/4/2022 MONICA RAMIREZ
Plan Check Approved 4/26/2022 MONICA RAMIREZ
Issued 7/13/2022 APPLICANT
CofO in Progress 7/15/2024 FREDDIE RIVERA
No Progress 8/13/2024 SCOTT FINNILA
CofO in Progress 8/13/2024 SCOTT FINNILA
CofO in Progress 8/13/2024 SCOTT FINNILA
Permit Finaled 9/16/2024 DEROLD HAUFF
CofO Issued 9/16/2024 DEROLD HAUFF
Permit Finaled 9/16/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/13/2022 CINDY QI
Sewer availability Cleared 1/13/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/18/2022 CINDY QI
Tenant Habitability Plan Cleared 1/18/2022 ISMAEL HERNANDEZ
Construction near power lines Cleared 4/6/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo A; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/20/2022 Approved FREDDIE RIVERA
Deputy Drilled-In Anchors 7/21/2022 Conditional Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 8/1/2022 Not Ready for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 8/1/2022 Not Ready for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 8/2/2022 Corrections Issued MICHAEL LEWIS
Deputy Drilled-In Anchors 8/3/2022 Conditional Approval MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 8/4/2022 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 8/8/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 8/18/2022 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 12/22/2022 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 12/22/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 12/22/2022 Corrections Issued FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 12/22/2022 Partial Inspection FREDDIE RIVERA
Special/Order Compliance 12/22/2022 Corrections Issued FREDDIE RIVERA
Wood Frame 12/22/2022 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 9/13/2023 Approved JUSTIN HAWLEY
HVAC-Rough 9/13/2023 Corrections Issued JUSTIN HAWLEY
PLUMBING-Rough 9/13/2023 Approved JUSTIN HAWLEY
Pre-Inspection 9/13/2023 Approved JUSTIN HAWLEY
Deputy Wood Construction 10/11/2023 Conditional Approval FREDDIE RIVERA
Insulation 10/19/2023 Approved FREDDIE RIVERA
Drywall Nailing 12/11/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/30/2024 Approved FREDDIE RIVERA
Final 5/30/2024 Corrections Issued FREDDIE RIVERA
MERV13>=Final 5/30/2024 Approved FREDDIE RIVERA
MERV13>=Rough 5/30/2024 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/30/2024 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 5/30/2024 Corrections Issued FREDDIE RIVERA
Final 6/21/2024 Partial Inspection FREDDIE RIVERA
Smoke Detectors 6/21/2024 Conditional Approval FREDDIE RIVERA
Final 7/15/2024 Partial Approval FREDDIE RIVERA
Smoke Detectors 7/15/2024 Approved FREDDIE RIVERA