7878 S AIRLANE AVE 90045
Certificate Information: 7878 S AIRLANE AVE 90045
- Application / Permit
- 21014-10000-06019
- Plan Check / Job No.
- B21LA22542
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2ND STORY STRUCTURE TO BE BUILD 1ST FLOOR AT THE BACK OF EXISTING GARAGE, 2ND FLOOR ON TOP OF EXISTING GARAGE AND STORAGE ROOM
- Permit Issued
- Issued on 7/8/2022
- Issuing Office
- Current Status
- Issued on 7/8/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2021 | JOE VO |
| Corrections Issued | 12/24/2021 | JOE VO |
| Quality Review Completed | 12/27/2021 | LIPING TENG |
| Applicant returned to address corrections | 5/23/2022 | JOE VO |
| Plan Check Approved | 7/8/2022 | JOE VO |
| Issued | 7/8/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/27/2022 | JOSE RODRIGUEZ |
| Construction near power lines | Cleared | 4/18/2022 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 5/17/2022 | KIRK LINKLATER |
| Specific Plan | Cleared | 5/23/2022 | EDUARDO HERMOSO |
| Low Impact Development | Cleared | 6/14/2022 | ANTHONY VARGAS |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 6/23/2022 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 6/27/2022 | CATHERINE ADROVER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/21/2022 | Approved | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 7/22/2022 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 7/26/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/22/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 10/20/2022 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 11/17/2022 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 11/17/2022 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 1/26/2023 | Partial Inspection | BOBBY KEY |
| Final | 6/2/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 6/2/2023 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 8/29/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 8/29/2023 | Conditional Approval | BOBBY KEY |
| HVAC-Rough | 8/29/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/29/2023 | Partial Approval | BOBBY KEY |
| Insulation | 9/12/2023 | Corrections Issued | RICHARD STEINBACH |
| Shower Pan | 9/12/2023 | Approved | RICHARD STEINBACH |
| Drywall Nailing | 10/19/2023 | Approved | BOBBY KEY |
| Insulation | 10/19/2023 | Approved | BOBBY KEY |