10520 1/2 S CROESUS AVE 90002
Certificate Information: 10520 1/2 S CROESUS AVE 90002
- Application / Permit
- 21014-10000-06015
- Plan Check / Job No.
- B21LA22532
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED [20 X 24] GARAGE TO ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A33(c),(d) AND (g). ADD [4'-6" X 10'-4"] TO THE REAR
- Permit Issued
- Issued on 5/17/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2021 | DANIEL SANJUAN |
| Corrections Issued | 12/7/2021 | DANIEL SANJUAN |
| Applicant returned to address corrections | 3/17/2022 | JESSE JIMENEZ |
| Applicant returned to address corrections | 4/29/2022 | RACHEL BEYENE |
| Building Plans Picked Up | 5/5/2022 | APPLICANT |
| Plan Check Approved | 5/17/2022 | ADAM HEGAZI |
| Issued | 5/17/2022 | APPLICANT |
| CofO in Progress | 10/20/2023 | JOHN KLARIN |
| CofO Issued | 10/20/2023 | ANSON MAGLASANG |
| Permit Finaled | 10/20/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2022 | KHOUNG LE |
| Address approval | Cleared | 3/4/2022 | KHOUNG LE |
| Roof/Waste drainage to street | Cleared | 3/4/2022 | KHOUNG LE |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2022 | KHOUNG LE |
| Sewer availability | Cleared | 3/9/2022 | KHOUNG LE |
| ZA Case | Cleared | 3/11/2022 | RYAN LY |
| ZA Case | Cleared | 3/11/2022 | RYAN LY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yassin,, Diaa Aldin; Lic. No.: C56295 | 2207 MERCED AVE SOUTH EL MONTE, CA 91733 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/19/2022 | Approved | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 11/10/2022 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 11/10/2022 | Not Ready for Inspection | JOHN KLARIN |
| Wood Frame | 11/10/2022 | Not Ready for Inspection | JOHN KLARIN |
| Deputy Drilled-In Anchors | 11/15/2022 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 11/17/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 5/18/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 5/18/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 5/18/2023 | Corrections Issued | JOHN KLARIN |
| Wood Frame | 5/18/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 6/1/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 6/1/2023 | Approved | JOHN KLARIN |
| Insulation | 6/5/2023 | Approved | JAMES CHAVEZ |
| Service/Power Release | 6/5/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Drywall Nailing | 6/28/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 6/28/2023 | Approved | JOHN KLARIN |
| Green Building Rough | 6/28/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 6/28/2023 | Approved | JOHN KLARIN |
| Service/Power Release | 6/28/2023 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/25/2023 | Approved | JOHN KLARIN |
| Final | 7/25/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 7/25/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/25/2023 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 7/25/2023 | Approved | JOHN KLARIN |
| Final | 7/31/2023 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 7/31/2023 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 10/19/2023 | Approved | JOHN KLARIN |
| Final | 10/19/2023 | OK to Issue CofO | JOHN KLARIN |
| HVAC-Final | 10/19/2023 | Approved | JOHN KLARIN |
| PLUMBING-Final | 10/19/2023 | Approved | JOHN KLARIN |
| Service/Power Release | 10/19/2023 | Approved | JOHN KLARIN |