13006 W VENTURA BLVD 91604
Certificate Information: 13006 W VENTURA BLVD 91604
- Application / Permit
- 21014-10000-06012
- Plan Check / Job No.
- B21LA22517
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1-STORY ADDITION TO THE REAR AND THE FRONT OF EXISTING SINGLE FAMILY DWELLING. SCOPE WILL ALSO INCLUDE A TRELLIS AT THE REAR WITH A UNCOVERED PATIO. 1 OF 2
- Permit Issued
- Issued on 10/14/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | MICHAEL LOPEZ |
| Corrections Issued | 1/13/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 1/19/2022 | KEN GILL |
| Building Plans Picked Up | 1/27/2022 | APPLICANT |
| Plan Check Approved | 7/15/2022 | MICHAEL LOPEZ |
| Issued | 10/14/2022 | APPLICANT |
| CofO in Progress | 1/2/2026 | RAUL OLAGI |
| Permit Finaled | 1/20/2026 | RUBEN SALAS |
| CofO Issued | 1/20/2026 | RUBEN SALAS |
| Permit Finaled | 1/20/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/2/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 6/17/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 7/2/2022 | JOHN LIN |
| ZI | Cleared | 7/5/2022 | STEVEN WECHSLER |
| GPI Written Notices | Cleared | 7/15/2022 | MICHAEL LOPEZ |
| Grading Pre-Inspection | Cleared | 7/15/2022 | MANUEL TEJADA |
Contact Information
| Contractor | Green Walls-Us Inc; Lic. No.: 798508-B | 22955 MARIANO ST WOODLAND HILLS, CA 91367 |
| Engineer | Yaprak,, Taskin Tolga; Lic. No.: C72927 | 560 31ST ST MANHATTAN BEACH, CA 90266 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/19/2024 | Approved | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 6/5/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/30/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 8/6/2024 | Approved | CHRISTOPHE COCHRAN |
| Pre-Inspection | 8/6/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 2/24/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 2/24/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2025 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 4/11/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 5/6/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 5/6/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 5/6/2025 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 5/6/2025 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 5/6/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 5/12/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 5/15/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 6/13/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Shower Pan | 6/13/2025 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 6/24/2025 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 6/27/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/27/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Drywall Nailing | 7/1/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 7/1/2025 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/12/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 11/12/2025 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 11/12/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 11/12/2025 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 11/12/2025 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/31/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 12/31/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 12/31/2025 | Approved | CHRISTOPHE COCHRAN |