6157 W BARROWS DR 90048
Certificate Information: 6157 W BARROWS DR 90048
- Application / Permit
- 21014-10000-05962
- Plan Check / Job No.
- B21LA22360
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 1-STORY GARAGE INTO A.D.U. PER STATE LAW. INCLUDES NEW STORAGE LOFT.
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- CofO Issued on 7/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 12/2/2021 | LAWRENCE QUIRANTE |
| Plan Check Approved | 1/19/2022 | JOSEPH RAFOLS |
| Issued | 2/3/2022 | APPLICANT |
| Building Plans Picked Up | 2/7/2022 | APPLICANT |
| CofO in Progress | 7/18/2022 | ADAM ESCOTO |
| Permit Finaled | 7/23/2022 | DEROLD HAUFF |
| Permit Finaled | 7/23/2022 | DEROLD HAUFF |
| CofO Issued | 7/23/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 12/9/2021 | JONATHAN KAPLAN |
| Address approval | Cleared | 12/13/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2021 | WALLIE JONG |
| Sewer availability | Cleared | 12/14/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/15/2022 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 3/15/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 3/15/2022 | Partial Approval | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 4/12/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 4/12/2022 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 4/12/2022 | Partial Approval | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2022 | Approved | ARTHUR SARGSYAN |
| Insulation | 4/29/2022 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 4/29/2022 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 5/3/2022 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 5/6/2022 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 7/11/2022 | Approved | ADAM ESCOTO |
| Final | 7/11/2022 | Corrections Issued | ADAM ESCOTO |
| Green Building Final | 7/11/2022 | Approved | ADAM ESCOTO |
| Green Building Rough | 7/11/2022 | Approved | ADAM ESCOTO |
| METHANE-Final | 7/11/2022 | Approved | ADAM ESCOTO |
| METHANE-Rough | 7/11/2022 | Approved | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 7/11/2022 | SGSOV Approved | ADAM ESCOTO |
| Smoke Detectors | 7/11/2022 | Approved | ADAM ESCOTO |
| Final | 7/18/2022 | OK to Issue CofO | ADAM ESCOTO |