6226 E MOUNT ANGELUS PL 1-4 90042

Certificate Information: 6226 E MOUNT ANGELUS PL 1-4 90042

Application / Permit
21014-10000-05959
Plan Check / Job No.
B21LA22347
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1) CONVERT EXISTING 530 sf COVERED DECK TO A FAMILY ROOM. 2) ADD 54 sf BALCONY AND STAIRCASE TO HAVE ACCESS TO BACKYARD. 3) REMODEL EXISTING 29 sf BALCONY & ADD 40 sf BALCONY ON FIRST FLOOR AND FIX THE STAIRCASE. 4) LEGALIZE (E) BATHROOM AND SECOND FLOOR. 5) ADD 530 sf OPEN ON ROOF.
Permit Issued
Issued on 9/29/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 JAD BASMA
Corrections Issued 3/18/2022 JAD BASMA
Quality Review Completed 3/18/2022 KEN GILL
Building Plans Picked Up 3/23/2022 APPLICANT
Applicant returned to address corrections 5/25/2022 JAD BASMA
Applicant returned to address corrections 6/6/2022 JAD BASMA
Plan Check Approved 6/14/2022 JAD BASMA
Issued 9/29/2022 APPLICANT
CofO in Progress 12/6/2024 LILIANA PORTILLO
CofO Issued 12/18/2024 DEROLD HAUFF
Permit Finaled 12/18/2024 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 5/12/2022 KATIE DEBIASE
BHO/Hillside ordinance Cleared 5/16/2022 CELINA MORENO
BHO/Hillside ordinance Cleared 5/16/2022 CELINA MORENO
BHO/Hillside ordinance Cleared 5/16/2022 CELINA MORENO
BHO/Hillside ordinance Cleared 5/16/2022 CELINA MORENO
BHO/Hillside ordinance Cleared 5/16/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/18/2022 CELINA MORENO
Low Impact Development Cleared 6/9/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/13/2022 CELINA MORENO
GPI Written Notices Cleared 9/29/2022 JAD BASMA

Contact Information

Contractor Owner-Builder       ,
Engineer David, Li & Associates; Lic. No.: C58075 1305 SAN GABRIEL BLVD   101    ROSEMEAD, CA 91770

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/26/2023 Not Ready for Inspection AMY COLIN
Deputy Reinf. Concrete 7/10/2023 Conditional Approval AMY COLIN
Wood Frame 9/13/2023 Corrections Issued AMY COLIN
Interior/Exterior Lathing 9/21/2023 Partial Approval JUSTIN HAWLEY
Shower Pan 9/21/2023 Corrections Issued JUSTIN HAWLEY
Interior/Exterior Lathing 10/4/2023 Partial Approval AMY COLIN
BUILDING-Rough-Frame 10/23/2023 Approved AMY COLIN
Drywall Nailing 10/23/2023 Approved AMY COLIN
Green Building Rough 10/23/2023 Approved AMY COLIN
Interior/Exterior Lathing 10/23/2023 Approved AMY COLIN
PLUMBING-Rough 12/20/2023 Corrections Issued AMY COLIN
Pre-Inspection 12/20/2023 Not Ready for Inspection AMY COLIN
SGSOV-Seismic Gas S/O Valve 4/30/2024 SGSOV Not Ready LILIANA PORTILLO
Final 5/6/2024 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 5/6/2024 Approved LILIANA PORTILLO
Green Building Final 5/6/2024 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/6/2024 SGSOV Approved LILIANA PORTILLO
Service/Power Release 5/6/2024 Not Required LILIANA PORTILLO
Smoke Detectors 5/6/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 7/18/2024 Approved LILIANA PORTILLO
Final 7/18/2024 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 7/18/2024 Approved LILIANA PORTILLO
PLUMBING-Final 7/18/2024 Approved LILIANA PORTILLO
Final 12/4/2024 OK to Issue CofO LILIANA PORTILLO