6142 W 75TH ST 90045
Certificate Information: 6142 W 75TH ST 90045
- Application / Permit
- 21014-10000-05915
- Plan Check / Job No.
- B21LA22219
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Existing detached garage covert to ADU Per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/23/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | JOSEPH RAFOLS |
| Corrections Issued | 12/2/2021 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 4/18/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 4/21/2022 | APPLICANT |
| Plan Check Approved | 5/12/2022 | KHUONG TRUONG |
| Issued | 6/23/2022 | APPLICANT |
| CofO in Progress | 5/18/2023 | RICHARD STEINBACH |
| Permit Finaled | 5/18/2023 | DANIEL ORRANTE |
| CofO Issued | 5/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/7/2022 | JONATHAN HOM |
| Address approval | Cleared | 1/21/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2022 | DINAH GARIN |
| Sewer availability | Cleared | 1/25/2022 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 4/7/2022 | DINAH GARIN |
| Specific Plan | Cleared | 5/3/2022 | FREDDY GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/19/2022 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2022 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/19/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Special/Order Compliance | 7/19/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 7/28/2022 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 8/4/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 8/4/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 8/8/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 9/9/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 9/9/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 9/9/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/9/2022 | Approved | BOBBY KEY |
| Underground Mechanical | 9/9/2022 | Conditional Approval | BOBBY KEY |
| Deputy Wood Construction | 9/15/2022 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 10/5/2022 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Approved | BOBBY KEY |
| Green Building Rough | 10/5/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/5/2022 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 10/21/2022 | Approved | BOBBY KEY |
| Insulation | 10/21/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/21/2022 | Approved | BOBBY KEY |
| Shower Pan | 10/21/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 10/31/2022 | Approved | RICHARD STEINBACH |
| ELECTRICAL-Final | 5/11/2023 | Approved | BOBBY KEY |
| Final | 5/11/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 5/11/2023 | Approved | BOBBY KEY |
| HVAC-Final | 5/11/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 5/11/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/11/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 5/11/2023 | Approved | BOBBY KEY |
| Final | 5/18/2023 | OK to Issue CofO | RICHARD STEINBACH |
| HVAC-Final | 5/18/2023 | Approved | RICHARD STEINBACH |