938 S MUIRFIELD ROAD 90019
Certificate Information: 938 S MUIRFIELD ROAD 90019
- Application / Permit
- 21014-10000-05900
- Plan Check / Job No.
- B21LA22139
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND AND SECOND FLOOR ADDITION AND INTERIOR RENOVATION TO (E) 2-STORY SFD
- Permit Issued
- Issued on 4/17/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | KHEDER ALRAZAA |
| Corrections Issued | 12/15/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 12/17/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/4/2022 | APPLICANT |
| Plan Check Approved | 8/8/2022 | KHEDER ALRAZAA |
| Issued | 4/17/2023 | APPLICANT |
| CofO in Progress | 7/31/2025 | JEFFREY MEAD |
| Permit Finaled | 8/3/2025 | DEROLD HAUFF |
| CofO Issued | 8/3/2025 | DEROLD HAUFF |
| Permit Finaled | 8/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/14/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 2/14/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2022 | TREVOR QUAN |
Contact Information
| Architect | Scrafano,, Elissa F; Lic. No.: C26071 | 163 N SYCAMORE LOS ANGELES, CA 90036 |
| Contractor | A R M Builders Inc; Lic. No.: 915352-B | 1080 S LA CIENEGA #311 LOS ANGELES, CA 90035 |
| Engineer | Kaligi,, Sean; Lic. No.: M37797 | 655 N CENTRAL AVE 17TH FL GLENDALE, CA 91203 |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/28/2023 | Conditional Approval | JEFFREY MEAD |
| Special/Order Compliance | 10/12/2023 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 10/27/2023 | Partial Approval | JEFFREY MEAD |
| METHANE-Barrier | 10/27/2023 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 10/27/2023 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 11/9/2023 | Approved | JEFFREY MEAD |
| Underground Mechanical | 12/18/2023 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 1/3/2024 | Approved | JEFFREY MEAD |
| Deputy Steel/Welding | 3/21/2024 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2024 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Partial Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 8/13/2024 | Conditional Approval | NICHOLAS LOPEZ |
| Deputy Steel/Welding | 8/13/2024 | Conditional Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 9/25/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 9/26/2024 | Approved | JEFFREY MEAD |
| HVAC-Rough | 10/8/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2024 | Partial Approval | BRENDAN MORELLI |
| Green Building Rough | 10/30/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| METHANE-Rough | 10/30/2024 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 11/5/2024 | Partial Approval | BRENDAN MORELLI |
| Green Building Rough | 11/5/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 11/5/2024 | Partial Approval | BRENDAN MORELLI |
| Interior/Exterior Lathing | 11/19/2024 | Approved | JEFFREY MEAD |
| Insulation | 12/9/2024 | Conditional Approval | JEFFREY MEAD |
| Drywall Nailing | 12/31/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 3/6/2025 | Approved | JEFFREY MEAD |
| Shower Pan | 3/6/2025 | Approved | JEFFREY MEAD |
| Underground Mechanical | 5/14/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 5/20/2025 | Corrections Issued | JEFFREY MEAD |
| Gas Test | 5/20/2025 | Approved | JEFFREY MEAD |
| Special/Order Compliance | 5/20/2025 | Approved | JEFFREY MEAD |
| Gas Test | 5/27/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/2/2025 | SGSOV Approved | JEFFREY MEAD |
| HVAC-Final | 6/9/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 6/16/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 6/16/2025 | Approved | JEFFREY MEAD |
| Service/Power Release | 6/16/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 6/25/2025 | Approved | JEFFREY MEAD |
| Final | 6/25/2025 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 6/25/2025 | Approved | JEFFREY MEAD |
| Smoke Detectors | 6/25/2025 | Approved | JEFFREY MEAD |
| Final | 7/8/2025 | Corrections Issued | JEFFREY MEAD |
| Final | 7/25/2025 | Corrections Issued | JEFFREY MEAD |
| Final | 7/30/2025 | OK to Issue CofO | JEFFREY MEAD |