7754 S HINDRY AVE 90045

Certificate Information: 7754 S HINDRY AVE 90045

Application / Permit
21014-10000-05895
Plan Check / Job No.
B21LA22129
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert an existing 213 sq. ft. attached garage to an ADU. and add to the ADU 277 sq.. ft. Total of 490 sq.. ft. of living area
Permit Issued
Issued on 3/16/2022
Issuing Office
Current Status
CofO Issued on 11/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2021 APPLICANT
Assigned to Plan Check Engineer 11/30/2021 JOE VO
Corrections Issued 11/30/2021 JOE VO
Applicant returned to address corrections 1/13/2022 JOE VO
Applicant returned to address corrections 1/18/2022 JOE VO
Plan Check Approved 3/16/2022 JOE VO
Issued 3/16/2022 APPLICANT
CofO in Progress 11/16/2022 BOBBY KEY
Permit Finaled 11/30/2022 DANIEL ORRANTE
CofO Issued 11/30/2022 DANIEL ORRANTE
Permit Finaled 11/30/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/10/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 1/30/2022 MAHELET GEBEYHU
Eng Process Fee Ord 176,300 Cleared 2/15/2022 HISASHI KOBAYAKAWA
Sewer availability Cleared 2/15/2022 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 3/10/2022 ROBERT HUGHES
Specific Plan Cleared 3/15/2022 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/23/2022 Corrections Issued BOBBY KEY
Excavation/Setback/Form/Re-Bar 3/23/2022 Partial Approval BOBBY KEY
PLUMBING-Rough 3/23/2022 Partial Approval BOBBY KEY
Deputy Drilled-In Anchors 4/1/2022 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 4/6/2022 Approved BOBBY KEY
ELECTRICAL-Final 5/9/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 5/9/2022 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/9/2022 Corrections Issued BOBBY KEY
PLUMBING-Rough 5/9/2022 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 5/19/2022 Approved BOBBY KEY
ELECTRICAL-Rough 5/19/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Approved BOBBY KEY
Green Building Rough 5/19/2022 Not Ready for Inspection BOBBY KEY
MERV13>=Rough 5/19/2022 Approved BOBBY KEY
PLUMBING-Rough 5/19/2022 Approved BOBBY KEY
Green Building Rough 5/26/2022 Approved BOBBY KEY
Interior/Exterior Lathing 5/26/2022 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 6/3/2022 Approved BOBBY KEY
Insulation 6/3/2022 Approved BOBBY KEY
Interior/Exterior Lathing 6/3/2022 Partial Approval BOBBY KEY
Shower Pan 6/3/2022 Approved BOBBY KEY
Drywall Nailing 6/13/2022 Approved BOBBY KEY
Final 6/13/2022 Corrections Issued BOBBY KEY
HVAC-Rough 6/13/2022 Approved BOBBY KEY
Interior/Exterior Lathing 6/13/2022 Approved BOBBY KEY
ELECTRICAL-Final 10/19/2022 Corrections Issued BOBBY KEY
Final 10/19/2022 Corrections Issued BOBBY KEY
Green Building Final 10/19/2022 Approved BOBBY KEY
HVAC-Final 10/19/2022 Corrections Issued BOBBY KEY
MERV13>=Final 10/19/2022 Approved BOBBY KEY
PLUMBING-Final 10/19/2022 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 10/19/2022 SGSOV Not Ready BOBBY KEY
Smoke Detectors 10/19/2022 Approved BOBBY KEY
Final 11/4/2022 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 11/4/2022 SGSOV Approved ANDREW NAVE
ELECTRICAL-Final 11/15/2022 Approved BOBBY KEY
Final 11/15/2022 OK to Issue CofO BOBBY KEY
HVAC-Final 11/15/2022 Approved BOBBY KEY
PLUMBING-Final 11/15/2022 Approved BOBBY KEY