6212 W LINDENHURST AVE 90048
Certificate Information: 6212 W LINDENHURST AVE 90048
- Application / Permit
- 21014-10000-05881
- Plan Check / Job No.
- B21LA22107
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT ADDITION TO (E) 1-STORY GARAGE PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 3/15/2022
- Issuing Office
- Current Status
- Issued on 3/15/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | DANIEL YIP |
| Corrections Issued | 12/14/2021 | DANIEL YIP |
| Quality Review Completed | 12/21/2021 | LIPING TENG |
| Applicant returned to address corrections | 1/26/2022 | DANIEL YIP |
| Applicant returned to address corrections | 2/23/2022 | DANIEL YIP |
| Plan Check Approved | 3/14/2022 | JOE VO |
| Issued | 3/15/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2022 | KHOUNG LE |
| Roof/Waste drainage to street | Cleared | 1/27/2022 | KHOUNG LE |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2022 | KHOUNG LE |
| Sewer availability | Cleared | 2/8/2022 | KHOUNG LE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Saljooghi,, Sanjar; Lic. No.: C53610 | 23265 PARK ENSENADA CALABASAS, CA 91302 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/2/2022 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/2/2022 | Partial Approval | MICHAEL PELHAM |
| METHANE-Barrier | 6/2/2022 | Approved | MICHAEL PELHAM |
| METHANE-Final | 6/2/2022 | Approved | MICHAEL PELHAM |
| METHANE-Rough | 6/2/2022 | Approved | MICHAEL PELHAM |
| METHANE-Subgrade | 6/2/2022 | Approved | MICHAEL PELHAM |
| PLUMBING-Rough | 6/6/2022 | Partial Approval | EVAN COOPER |
| Deputy Reinf. Concrete | 6/17/2022 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 6/17/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 8/26/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Sewer | 8/26/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 8/26/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Corrections Issued | MICHAEL PELHAM |
| ELECTRICAL-Rough | 9/14/2022 | Not Ready for Inspection | MICHAEL PELHAM |
| Underground Mechanical | 9/14/2022 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2022 | Not Ready for Inspection | ANDREW NAVE |
| BUILDING-Rough-Frame | 9/19/2022 | Corrections Issued | ANDREW NAVE |
| Deputy Wood Construction | 9/19/2022 | Conditional Approval | ANDREW NAVE |
| Green Building Rough | 9/19/2022 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Rough | 12/22/2022 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 2/6/2023 | Conditional Approval | JEREMY TODD |
| Green Building Rough | 2/6/2023 | Not Ready for Inspection | JEREMY TODD |
| Interior/Exterior Lathing | 4/17/2023 | Corrections Issued | MICHAEL PELHAM |
| Interior/Exterior Lathing | 4/18/2023 | Not Ready for Inspection | JEREMY TODD |
| Interior/Exterior Lathing | 4/27/2023 | Approved | JEREMY TODD |
| Insulation | 5/24/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 6/1/2023 | Approved | JEREMY TODD |
| Green Building Rough | 6/1/2023 | Approved | JEREMY TODD |