2663 E MERCED ST 90065

Certificate Information: 2663 E MERCED ST 90065

Application / Permit
21014-10000-05851
Plan Check / Job No.
B21LA21950
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached 1 car garage to an adu with addition PER LAMC 12.22 A33 (c) AND (d)
Permit Issued
Issued on 6/9/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 DANIEL SANJUAN
Corrections Issued 12/9/2021 DANIEL SANJUAN
Applicant returned to address corrections 3/4/2022 RAHEL BEYENE
Applicant returned to address corrections 3/7/2022 RAHEL BEYENE
Plan Check Approved 4/5/2022 SAMUEL GONZALEZ
Building Plans Picked Up 4/7/2022 APPLICANT
Issued 6/9/2022 APPLICANT
CofO in Progress 8/7/2024 CRAIG VAUGHAN
CofO Issued 9/17/2024 DEROLD HAUFF
Permit Finaled 9/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/29/2021 TREVOR QUAN
Roof/Waste drainage to street Cleared 12/29/2021 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 1/25/2022 TREVOR QUAN
Sewer availability Cleared 1/25/2022 TREVOR QUAN
Supp. Use District POD/CDO/TDO Cleared 2/24/2022 NASHYA JENSEN
ZI Cleared 2/24/2022 NASHYA JENSEN
Grading Pre-Inspection Cleared 3/10/2022 DANIEL SANJUAN

Contact Information

Contractor A And G Construction Solutions Inc; Lic. No.: 1086246-B 4743 EAGLE ROCK BLVD      LOS ANGELES, CA 90041

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/25/2022 Partial Approval CRAIG VAUGHAN
Pre-Inspection 7/27/2022 Approved OSVALDO PARAMO
Footing/Foundation/Slab 8/31/2022 Corrections Issued OSVALDO PARAMO
Underground Mechanical 12/6/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 12/20/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 1/19/2023 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 1/19/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Rough-Elec/Plmb/HVAC 1/19/2023 Corrections Issued KATHRYN BUTTERWORTH
Deputy Drilled-In Anchors 1/20/2023 Approved OSVALDO PARAMO
ELECTRICAL-Rough 1/20/2023 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 1/20/2023 Approved OSVALDO PARAMO
ELECTRICAL-Rough 1/24/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 1/25/2023 Approved ALIZAH MAYAGOITIA
Green Building Rough 1/25/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 1/25/2023 Approved ALIZAH MAYAGOITIA
Insulation 1/26/2023 Approved OSVALDO PARAMO
Drywall Nailing 1/31/2023 Approved OSVALDO PARAMO
Final 5/5/2023 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 5/5/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/5/2023 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 5/5/2023 Approved ALIZAH MAYAGOITIA
Final 5/12/2023 Corrections Issued OSVALDO PARAMO
Green Building Final 5/12/2023 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/12/2023 SGSOV Approved OSVALDO PARAMO
Final 6/5/2023 Corrections Issued OSVALDO PARAMO
Final 6/12/2023 Conditional Approval OSVALDO PARAMO
Service/Power Release 6/12/2023 Approved OSVALDO PARAMO
ELECTRICAL-Final 8/6/2024 Approved CRAIG VAUGHAN
Final 8/6/2024 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 8/6/2024 Approved CRAIG VAUGHAN
PLUMBING-Final 8/6/2024 Approved CRAIG VAUGHAN