11947 W BEATRICE ST 90230

Certificate Information: 11947 W BEATRICE ST 90230

Application / Permit
21014-10000-05850
Plan Check / Job No.
B21LA21927
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SECOND STORY ADDITION (752 SF) TO (E) SFD AND REMODEL OF 1ST FLOOR.
Permit Issued
Issued on 5/6/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 VIVIAN LAO
Corrections Issued 12/15/2021 VIVIAN LAO
Quality Review Completed 12/22/2021 KEN GILL
Building Plans Picked Up 12/27/2021 APPLICANT
Applicant returned to address corrections 4/4/2022 VIVIAN LAO
Plan Check Approved 5/6/2022 VIVIAN LAO
Issued 5/6/2022 APPLICANT
CofO in Progress 8/18/2023 HERBERT GIRON
Permit Finaled 8/22/2023 DANIEL ORRANTE
CofO Issued 8/22/2023 DANIEL ORRANTE
Permit Finaled 8/22/2023 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 1/5/2022 RAYMOND MUGAMBWA
Eng Process Fee Ord 176,300 Cleared 1/11/2022 RAYMOND MUGAMBWA
Specific Plan Cleared 1/20/2022 PETE EYRE
Low Impact Development Cleared 4/19/2022 SUNG JOON WON

Contact Information

Contractor Lio James Construction Inc; Lic. No.: 1062961-B 18375 VENTURA BLVD #716      TARZANA, CA 91356
Engineer Adefeso,, Wole Dayo; Lic. No.: C63361 1620 CENTINELA AVE 3048      INGLEWOOD, CA 90302

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/24/2022 Conditional Approval CLAYTON GRAHAM
Footing/Foundation/Slab 5/31/2022 Approved JESUS RODRIGUEZ
METHANE-Barrier 5/31/2022 Approved JESUS RODRIGUEZ
METHANE-Subgrade 5/31/2022 Approved JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 6/9/2022 Partial Approval JESUS RODRIGUEZ
Deputy Reinf. Concrete 6/13/2022 Conditional Approval JESUS RODRIGUEZ
Reinforced Concrete Frame 7/1/2022 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/8/2022 Approved JESUS RODRIGUEZ
Structural Steel Frame 7/8/2022 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 9/30/2022 Corrections Issued HERBERT GIRON
PLUMBING-Rough 9/30/2022 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 10/7/2022 Approved HERBERT GIRON
PLUMBING-Final 10/7/2022 Corrections Issued HERBERT GIRON
PLUMBING-Rough 10/7/2022 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Approved HERBERT GIRON
HVAC-Rough 10/13/2022 Corrections Issued HERBERT GIRON
Deputy Wood Construction 10/14/2022 Conditional Approval MICHAEL PELHAM
Interior/Exterior Lathing 11/7/2022 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 11/15/2022 Conditional Approval HERBERT GIRON
Green Building Rough 11/15/2022 Approved HERBERT GIRON
HVAC-Rough 11/15/2022 Approved HERBERT GIRON
MERV13>=Rough 11/15/2022 Approved HERBERT GIRON
METHANE-Rough 11/15/2022 Approved HERBERT GIRON
Special/Order Compliance 11/15/2022 Corrections Issued HERBERT GIRON
Verify Sprinkler Sign Off 11/15/2022 Approved HERBERT GIRON
Insulation 11/23/2022 Conditional Approval HERBERT GIRON
Drywall Nailing 12/21/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 2/1/2023 Approved HERBERT GIRON
Shower Pan 2/1/2023 Approved HERBERT GIRON
Gas Test 6/23/2023 Approved HERBERT GIRON
PLUMBING-Final 6/23/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 6/28/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 6/28/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 7/6/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 7/6/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 7/18/2023 Partial Approval RICHARD STEINBACH
HVAC-Final 7/18/2023 Not Ready for Inspection RICHARD STEINBACH
PLUMBING-Final 7/18/2023 Approved RICHARD STEINBACH
ELECTRICAL-Final 7/21/2023 Approved HERBERT GIRON
HVAC-Final 7/21/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 7/28/2023 Approved HERBERT GIRON
Final 7/28/2023 Corrections Issued HERBERT GIRON
Green Building Final 7/28/2023 Approved HERBERT GIRON
HVAC-Final 7/28/2023 Approved HERBERT GIRON
MERV13>=Final 7/28/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 7/28/2023 SGSOV Approved HERBERT GIRON
Sewer 7/28/2023 Approved HERBERT GIRON
Smoke Detectors 7/28/2023 Corrections Issued HERBERT GIRON
Final 8/4/2023 Corrections Issued HERBERT GIRON
HVAC-Final 8/4/2023 Approved HERBERT GIRON
Smoke Detectors 8/4/2023 Approved HERBERT GIRON
Final 8/18/2023 OK to Issue CofO HERBERT GIRON
Service/Power Release 8/18/2023 Approved HERBERT GIRON