6417 S ARLINGTON AVE 90043

Certificate Information: 6417 S ARLINGTON AVE 90043

Application / Permit
21014-10000-05834
Plan Check / Job No.
B21LA21867
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 2-STORY A.D.U. TO AN (E) GARAGE Per LAMC 12.22 A.33 (c) (d)
Permit Issued
Issued on 5/18/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2021 APPLICANT
Corrections Issued 11/25/2021 FERNANDO FLORES
Assigned to Plan Check Engineer 11/30/2021 FERNANDO FLORES
Corrections Issued 2/23/2022 FERNANDO FLORES
Applicant returned to address corrections 4/20/2022 FERNANDO FLORES
Building Plans Picked Up 4/21/2022 APPLICANT
Plan Check Approved 5/18/2022 KHUONG TRUONG
Issued 5/18/2022 APPLICANT
CofO in Progress 9/29/2023 ENRIQUE MIRELES
CofO in Progress 9/29/2023 ENRIQUE MIRELES
CofO Issued 10/9/2023 DEROLD HAUFF
Permit Finaled 10/9/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/15/2021 ABEL CASILLAS
Construction near power lines Cleared 2/17/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 2/22/2022 ABEL CASILLAS
Sewer availability Cleared 2/22/2022 ABEL CASILLAS
Low Impact Development Cleared 3/31/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 4/25/2022 ABEL CASILLAS

Contact Information

Contractor R H Construction Corp; Lic. No.: 1049468-B 6418 REGENT STREET APARTMENT A      HUNTINGTON PARK, CA 90255
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 866      HAWTHORNE, CA 90251

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/7/2022 Corrections Issued JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 6/9/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 6/9/2022 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 2/1/2023 Approved ENRIQUE MIRELES
Service/Power Release 6/8/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/4/2023 Approved ENRIQUE MIRELES
Final 8/4/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 8/4/2023 Approved ENRIQUE MIRELES
Green Building Final 8/4/2023 Approved ENRIQUE MIRELES
Green Building Rough 8/4/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/4/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 8/4/2023 Approved ENRIQUE MIRELES
Final 8/31/2023 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Final 9/13/2023 Approved JUSTIN HAWLEY
Final 9/13/2023 Not Ready for Inspection JUSTIN HAWLEY
HVAC-Final 9/13/2023 Approved JUSTIN HAWLEY
PLUMBING-Final 9/13/2023 Approved JUSTIN HAWLEY
Final 9/28/2023 OK to Issue CofO ENRIQUE MIRELES