243-245 W 75TH ST 90003

Certificate Information: 243-245 W 75TH ST 90003

Application / Permit
21014-10000-05822
Plan Check / Job No.
B21LA21789
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERSION OF (E) ATTACHED GARAGE TO AN ADU, WITH ADDITION PER LAMC 12.22 A.33(c) AND (e). REPAIR (E) GARAGE WALLS AND ROOF FROM FIRE DAMAGE.
Permit Issued
Issued on 2/9/2022
Issuing Office
Current Status
CofO Issued on 5/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2021 APPLICANT
Assigned to Plan Check Engineer 11/22/2021 DANIEL SANJUAN
Corrections Issued 11/23/2021 DANIEL SANJUAN
Issued 2/9/2022 APPLICANT
Building Plans Picked Up 2/10/2022 APPLICANT
CofO in Progress 4/2/2025 JOHN QUINTANILLA
No Progress 4/5/2025 DEROLD HAUFF
CofO in Progress 4/5/2025 DEROLD HAUFF
CofO Issued 5/16/2025 DEROLD HAUFF
Permit Finaled 5/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/2/2021 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 12/3/2021 JEANETTE VONG
Roof/Waste drainage to street Cleared 12/3/2021 JEANETTE VONG
Sewer availability Cleared 12/3/2021 JEANETTE VONG

Contact Information

Contractor Jerahian Araz; Lic. No.: 1045340-B 250 N COLLEGE PARK DR F36      UPLAND, CA 91786
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/14/2023 Corrections Issued LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 4/26/2023 Corrections Issued LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 12/14/2023 Partial Inspection MICHAEL LEWIS
Footing/Foundation/Slab 12/14/2023 Partial Inspection MICHAEL LEWIS
Underground Mechanical 12/14/2023 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 5/22/2024 Corrections Issued MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 5/30/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 5/30/2024 Approved MICHAEL LEWIS
Underground Mechanical 5/30/2024 Approved MICHAEL LEWIS
ELECTRICAL-Rough 6/27/2024 Corrections Issued MICHAEL LEWIS
HVAC-Rough 6/27/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 6/27/2024 Approved MICHAEL LEWIS
Wood Frame 6/27/2024 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 7/5/2024 Not Ready for Inspection CRAIG DAVIS
Green Building Rough 7/5/2024 Not Ready for Inspection CRAIG DAVIS
MERV13>=Rough 7/5/2024 Not Ready for Inspection CRAIG DAVIS
Wood Frame 7/5/2024 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 7/10/2024 Partial Approval MICHAEL LEWIS
ELECTRICAL-Rough 7/10/2024 Approved MICHAEL LEWIS
Wood Frame 7/10/2024 Approved MICHAEL LEWIS
Insulation 8/8/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 8/8/2024 Approved MICHAEL LEWIS
Drywall Nailing 8/15/2024 Approved ALEX COLIN
Interior/Exterior Lathing 9/17/2024 Approved ALEX COLIN
Shower Pan 9/17/2024 Approved ALEX COLIN
SGSOV-Seismic Gas S/O Valve 11/26/2024 SGSOV Not Ready MICHAEL LEWIS
BUILDING-Rough-Frame 12/6/2024 Approved MICHAEL LEWIS
Final 12/6/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 12/6/2024 Approved MICHAEL LEWIS
Green Building Rough 12/6/2024 Approved MICHAEL LEWIS
MERV13>=Final 12/6/2024 Approved MICHAEL LEWIS
MERV13>=Rough 12/6/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/6/2024 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 12/6/2024 Corrections Issued MICHAEL LEWIS
Final 12/18/2024 Not Ready for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 12/18/2024 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 12/18/2024 Not Ready for Inspection JOHN QUINTANILLA
Final 1/7/2025 No Access for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 1/7/2025 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 1/7/2025 No Access for Inspection JOHN QUINTANILLA
Final 1/23/2025 Corrections Issued JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 1/23/2025 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 1/23/2025 Corrections Issued JOHN QUINTANILLA
Final 1/28/2025 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 1/28/2025 Approved MICHAEL LEWIS
Final 2/19/2025 Conditional Approval JOHN QUINTANILLA
Final 3/10/2025 OK to Issue CofO JOHN QUINTANILLA
HVAC-Final 4/10/2025 Approved JOHN QUINTANILLA
Service/Power Release 4/24/2025 Approved JOHN QUINTANILLA