2957 S HILLCREST DR 90016

Certificate Information: 2957 S HILLCREST DR 90016

Application / Permit
21014-10000-05821
Plan Check / Job No.
B21LA21788
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-story ADU addition attached to existing SFD.
Permit Issued
Issued on 3/3/2022
Issuing Office
Current Status
CofO Issued on 11/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 JOE VO
Corrections Issued 11/25/2021 JOE VO
Plan Check Approved 2/28/2022 JOE VO
Issued 3/3/2022 APPLICANT
CofO in Progress 9/30/2024 JUSTIN HAWLEY
Permit Finaled 11/16/2024 DEROLD HAUFF
CofO Issued 11/16/2024 DEROLD HAUFF
Permit Finaled 11/16/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/9/2021 AMAAN MALIK
Roof/Waste drainage to street Cleared 12/9/2021 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 12/14/2021 AMAAN MALIK
Sewer availability Cleared 12/14/2021 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,
Engineer Song,, Zhenyu Michael; Lic. No.: NA5266       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/1/2022 Conditional Approval STUART CHAPMAN
PLUMBING-Rough 7/5/2022 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 7/8/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 7/8/2022 Approved STUART CHAPMAN
Pre-Inspection 8/5/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 10/6/2022 Approved STUART CHAPMAN
PLUMBING-Rough 10/6/2022 Approved STUART CHAPMAN
Wood Frame 10/6/2022 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Partial Approval STUART CHAPMAN
Insulation 10/17/2022 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 10/24/2022 Approved STUART CHAPMAN
Green Building Rough 10/24/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 10/24/2022 Partial Approval STUART CHAPMAN
Insulation 10/28/2022 Approved STUART CHAPMAN
Drywall Nailing 11/8/2022 Approved STUART CHAPMAN
Shower Pan 11/8/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 11/15/2022 Partial Approval STUART CHAPMAN
Final 3/7/2023 Corrections Issued CALEB MEISTER
Green Building Final 3/7/2023 Not Ready for Inspection CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Approved CALEB MEISTER
Smoke Detectors 3/7/2023 Approved CALEB MEISTER
Final 3/20/2023 Corrections Issued CALEB MEISTER
Green Building Final 3/20/2023 Not Ready for Inspection CALEB MEISTER
Final 9/11/2024 Corrections Issued JUSTIN HAWLEY
Green Building Final 9/11/2024 Not Ready for Inspection JUSTIN HAWLEY
ELECTRICAL-Final 9/30/2024 Approved JUSTIN HAWLEY
Final 9/30/2024 OK to Issue CofO JUSTIN HAWLEY
Green Building Final 9/30/2024 Approved JUSTIN HAWLEY
HVAC-Final 9/30/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 9/30/2024 Approved JUSTIN HAWLEY