160 W 88TH PL 90003
Certificate Information: 160 W 88TH PL 90003
- Application / Permit
- 21014-10000-05757
- Plan Check / Job No.
- B21LA21607
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXISTING Dwelling TO REMAIN. ADDING 2 CAR GARAGE ON THE FIRST FLOOR AND 2ND FLOOR ADDITION
- Permit Issued
- Issued on 8/4/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | KHUONG TRUONG |
| Corrections Issued | 12/22/2021 | KHUONG TRUONG |
| Quality Review Completed | 12/30/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/5/2022 | APPLICANT |
| Applicant returned to address corrections | 1/19/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 2/4/2022 | KHUONG TRUONG |
| Plan Check Approved | 8/4/2022 | KHUONG TRUONG |
| Issued | 8/4/2022 | APPLICANT |
| CofO in Progress | 1/10/2024 | MICHAEL LEWIS |
| Permit Finaled | 1/13/2024 | DEROLD HAUFF |
| CofO Issued | 1/13/2024 | DEROLD HAUFF |
| Permit Finaled | 1/13/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 2/8/2022 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 7/14/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 7/29/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/6/2022 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/15/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 9/15/2022 | Corrections Issued | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 9/22/2022 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 9/22/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 9/22/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 11/30/2022 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 11/30/2022 | Corrections Issued | LILIANA PORTILLO |
| Deputy Wood Construction | 12/1/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/5/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 12/5/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 12/5/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 12/23/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/3/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 1/3/2023 | Approved | LILIANA PORTILLO |
| Insulation | 1/10/2023 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/10/2023 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/9/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 2/9/2023 | Approved | LILIANA PORTILLO |
| Green Building Rough | 2/9/2023 | Approved | LILIANA PORTILLO |
| Insulation | 2/9/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 2/9/2023 | Approved | LILIANA PORTILLO |
| Final | 3/31/2023 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 3/31/2023 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 3/31/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Final | 5/2/2023 | Corrections Issued | MICHAEL LEWIS |
| Final | 5/2/2023 | Partial Inspection | MICHAEL LEWIS |
| Green Building Final | 5/2/2023 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 5/2/2023 | Partial Inspection | MICHAEL LEWIS |
| ELECTRICAL-Final | 5/8/2023 | Approved | MICHAEL LEWIS |
| Final | 12/22/2023 | Conditional Approval | MICHAEL LEWIS |
| Smoke Detectors | 12/22/2023 | Approved | MICHAEL LEWIS |
| Final | 1/9/2024 | OK to Issue CofO | MICHAEL LEWIS |