1418 N LUCILE AVE 90026

Certificate Information: 1418 N LUCILE AVE 90026

Application / Permit
21014-10000-05734
Plan Check / Job No.
B21LA21548
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN CHECK* CONVERT (E) (368 SF) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 12/13/2021
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2021 APPLICANT
Assigned to Plan Check Engineer 11/16/2021 VIVIAN LAO
Corrections Issued 11/17/2021 VIVIAN LAO
Applicant returned to address corrections 11/23/2021 VIVIAN LAO
Applicant returned to address corrections 12/1/2021 VIVIAN LAO
Plan Check Approved 12/8/2021 SELLA BENYAMIN
Issued 12/13/2021 APPLICANT
CofO in Progress 11/23/2022 FREDDIE RIVERA
Permit Finaled 3/4/2023 DANIEL ORRANTE
CofO Issued 3/4/2023 DANIEL ORRANTE
Permit Finaled 3/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/23/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/23/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 11/23/2021 JEANIE LAM
Sewer availability Cleared 11/23/2021 JEANIE LAM
Grading Pre-Inspection Cleared 12/8/2021 VIVIAN LAO

Contact Information

Contractor Excel Construction L A Inc; Lic. No.: 998499-B       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/17/2022 Corrections Issued AMY COLIN
BUILDING-Rough-Frame 2/28/2022 Not Ready for Inspection ADAM ESCOTO
Footing/Foundation/Slab 2/28/2022 Not Ready for Inspection ADAM ESCOTO
Green Building Rough 2/28/2022 Not Ready for Inspection ADAM ESCOTO
PLUMBING-Rough 2/28/2022 Not Ready for Inspection ADAM ESCOTO
Excavation/Setback/Form/Re-Bar 3/23/2022 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 3/29/2022 No Access for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 3/29/2022 Not Ready for Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 3/29/2022 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 3/29/2022 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 3/29/2022 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 3/29/2022 Partial Approval FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 3/29/2022 Not Ready for Inspection FREDDIE RIVERA
Deputy Drilled-In Anchors 4/1/2022 No Result Entered ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 4/6/2022 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 4/11/2022 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 4/11/2022 Approved FREDDIE RIVERA
ELECTRICAL-Rough 4/14/2022 Partial Approval FREDDIE RIVERA
Masonry Wall/Backfill 4/14/2022 Approved FREDDIE RIVERA
ELECTRICAL-Rough 5/11/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 5/11/2022 Approved FREDDIE RIVERA
Wood Frame 5/11/2022 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 5/17/2022 Conditional Approval FREDDIE RIVERA
Green Building Rough 5/17/2022 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 6/1/2022 Approved FREDDIE RIVERA
Drywall Nailing 6/1/2022 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Approved FREDDIE RIVERA
Green Building Rough 6/1/2022 Approved FREDDIE RIVERA
Insulation 6/1/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 6/1/2022 Approved FREDDIE RIVERA
Drywall Nailing 6/6/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Drywall Nailing 6/9/2022 Partial Approval FREDDIE RIVERA
Interior/Exterior Lathing 6/9/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 6/9/2022 Corrections Issued FREDDIE RIVERA
Shower Pan 6/29/2022 Corrections Issued FREDDIE RIVERA
Shower Pan 7/5/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/2/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Drywall Nailing 11/7/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 11/7/2022 Approved FREDDIE RIVERA
Final 11/7/2022 Corrections Issued FREDDIE RIVERA
Green Building Final 11/7/2022 Partial Inspection FREDDIE RIVERA
HVAC-Final 11/7/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 11/7/2022 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/7/2022 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 11/7/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 11/15/2022 Approved FREDDIE RIVERA
Final 11/15/2022 Partial Inspection FREDDIE RIVERA
Green Building Final 11/15/2022 Corrections Issued FREDDIE RIVERA
HVAC-Final 11/15/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 11/15/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 11/22/2022 Approved FREDDIE RIVERA
Final 11/22/2022 OK to Issue CofO FREDDIE RIVERA
Green Building Final 11/22/2022 Approved FREDDIE RIVERA
HVAC-Final 11/22/2022 Approved FREDDIE RIVERA
PLUMBING-Final 11/22/2022 Approved FREDDIE RIVERA