Deputy Drilled-In Anchors
|
9/7/2022
|
Partial Approval
|
MATT KELLERMAN
|
|
Footing/Foundation/Slab
|
9/8/2022
|
Corrections Issued
|
THOMAS FINNILA
|
|
Deputy Reinf. Concrete
|
9/9/2022
|
Conditional Approval
|
DAVID MATSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/21/2022
|
Partial Approval
|
THOMAS FINNILA
|
|
ELECTRICAL-Rough
|
10/17/2022
|
Partial Approval
|
JACK KARGODORIAN
|
|
Excavation/Setback/Form/Re-Bar
|
10/17/2022
|
Partial Approval
|
JACK KARGODORIAN
|
|
Footing/Foundation/Slab
|
10/17/2022
|
Partial Approval
|
JACK KARGODORIAN
|
|
PLUMBING-Rough
|
10/17/2022
|
Partial Approval
|
JACK KARGODORIAN
|
|
Deputy Reinf. Concrete
|
10/19/2022
|
Partial Approval
|
JACK KARGODORIAN
|
|
Excavation/Setback/Form/Re-Bar
|
11/2/2022
|
Partial Approval
|
JACK KARGODORIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/2/2022
|
Partial Approval
|
JACK KARGODORIAN
|
|
Footing/Foundation/Slab
|
11/2/2022
|
Partial Approval
|
JACK KARGODORIAN
|
|
Deputy Reinf. Concrete
|
11/3/2022
|
Conditional Approval
|
MICHAEL SMITH
|
|
HVAC-Rough
|
11/14/2022
|
Partial Approval
|
JACK KARGODORIAN
|
|
Excavation/Setback/Form/Re-Bar
|
11/17/2022
|
Partial Approval
|
JACK KARGODORIAN
|
|
Footing/Foundation/Slab
|
11/17/2022
|
Partial Approval
|
JACK KARGODORIAN
|
|
Deputy Reinf. Concrete
|
11/18/2022
|
Partial Approval
|
JACK KARGODORIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/22/2022
|
Partial Approval
|
ROBERT GOLD
|
|
Excavation/Setback/Form/Re-Bar
|
11/30/2022
|
Partial Approval
|
DAVID MATSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/30/2022
|
Partial Approval
|
DAVID MATSON
|
|
Footing/Foundation/Slab
|
11/30/2022
|
Partial Approval
|
DAVID MATSON
|
|
Deputy Reinf. Concrete
|
12/2/2022
|
Conditional Approval
|
DAVID MATSON
|
|
PLUMBING-Rough
|
12/20/2022
|
Partial Approval
|
JACK KARGODORIAN
|
|
Underground Mechanical
|
12/20/2022
|
Partial Approval
|
JACK KARGODORIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/3/2023
|
Partial Approval
|
JACK KARGODORIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/13/2023
|
Corrections Issued
|
JACK KARGODORIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/13/2023
|
Off-Hour Fees Due
|
|
|
Special/Order Compliance
|
1/19/2023
|
Not Ready for Inspection
|
JACK KARGODORIAN
|
|
Special/Order Compliance
|
1/20/2023
|
Partial Approval
|
JACK KARGODORIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/24/2023
|
Partial Approval
|
JACK KARGODORIAN
|
|
Pre-Inspection
|
2/1/2023
|
Partial Approval
|
JACK KARGODORIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/21/2023
|
Partial Approval
|
JACK KARGODORIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/6/2023
|
Partial Approval
|
JACK KARGODORIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/17/2023
|
Partial Approval
|
JACK KARGODORIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/6/2023
|
Corrections Issued
|
JACK KARGODORIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/11/2023
|
Partial Approval
|
JACK KARGODORIAN
|
|
PLUMBING-Rough
|
4/25/2023
|
Corrections Issued
|
JACK KARGODORIAN
|
|
PLUMBING-Rough
|
4/28/2023
|
Approved
|
THOMAS FINNILA
|
|
HVAC-Rough
|
5/24/2023
|
Corrections Issued
|
THOMAS FINNILA
|
|
ELECTRICAL-Rough
|
5/26/2023
|
Corrections Issued
|
THOMAS FINNILA
|
|
HVAC-Rough
|
5/30/2023
|
Partial Approval
|
JACK KARGODORIAN
|
|
BUILDING-Rough-Frame
|
5/31/2023
|
Partial Approval
|
JACK KARGODORIAN
|
|
Green Building Rough
|
5/31/2023
|
Approved
|
JACK KARGODORIAN
|
|
Shower Pan
|
6/7/2023
|
Partial Approval
|
JACK KARGODORIAN
|
|
BUILDING-Rough-Frame
|
6/12/2023
|
Approved
|
JACK KARGODORIAN
|
|
Interior/Exterior Lathing
|
6/20/2023
|
Partial Approval
|
JACK KARGODORIAN
|
|
Shower Pan
|
6/20/2023
|
Partial Approval
|
JACK KARGODORIAN
|
|
Drywall Nailing
|
6/28/2023
|
Approved
|
RYAN SALAZAR
|
|
Insulation
|
6/28/2023
|
Approved
|
RYAN SALAZAR
|
|
Interior/Exterior Lathing
|
7/5/2023
|
Partial Approval
|
JACK KARGODORIAN
|
|
Shower Pan
|
7/5/2023
|
Approved
|
JACK KARGODORIAN
|
|
Interior/Exterior Lathing
|
7/21/2023
|
Partial Approval
|
JACK KARGODORIAN
|
|
Gas Test
|
10/3/2023
|
Approved
|
THOMAS FINNILA
|
|
ELECTRICAL-Final
|
10/25/2023
|
Approved
|
JUAN VALENZUELA
|
|
HVAC-Final
|
10/25/2023
|
Not Ready for Inspection
|
JUAN VALENZUELA
|
|
HVAC-Final
|
10/31/2023
|
Not Ready for Inspection
|
JOHN COLEMAN
|
|
PLUMBING-Final
|
10/31/2023
|
Approved
|
JOHN COLEMAN
|
|
HVAC-Final
|
11/3/2023
|
Approved
|
JOHN COLEMAN
|
|
PLUMBING-Final
|
11/3/2023
|
Approved
|
JOHN COLEMAN
|
|
BUILDING-Rough-Frame
|
12/19/2023
|
Not Ready for Inspection
|
KIRK SANDERS
|
|
Final
|
12/19/2023
|
Corrections Issued
|
KIRK SANDERS
|
|
Footing/Foundation/Slab
|
12/19/2023
|
Not Ready for Inspection
|
KIRK SANDERS
|
|
Green Building Final
|
12/19/2023
|
Not Ready for Inspection
|
KIRK SANDERS
|
|
SGSOV-Seismic Gas S/O Valve
|
12/19/2023
|
SGSOV Not Ready
|
KIRK SANDERS
|
|
Smoke Detectors
|
12/19/2023
|
Not Ready for Inspection
|
KIRK SANDERS
|
|
Verify Sprinkler Sign Off
|
12/19/2023
|
Not Ready for Inspection
|
KIRK SANDERS
|
|
BUILDING-Rough-Frame
|
1/10/2024
|
Approved
|
JOHN COLEMAN
|
|
Final
|
1/10/2024
|
Partial Inspection
|
JOHN COLEMAN
|
|
Footing/Foundation/Slab
|
1/10/2024
|
Approved
|
JOHN COLEMAN
|
|
Green Building Final
|
1/10/2024
|
Corrections Issued
|
JOHN COLEMAN
|
|
SGSOV-Seismic Gas S/O Valve
|
1/10/2024
|
SGSOV Approved
|
JOHN COLEMAN
|
|
Smoke Detectors
|
1/10/2024
|
Approved
|
JOHN COLEMAN
|
|
Verify Sprinkler Sign Off
|
1/10/2024
|
Approved
|
JOHN COLEMAN
|
|
Service/Power Release
|
1/11/2024
|
Approved
|
JOHN COLEMAN
|
|
Final
|
1/26/2024
|
OK to Issue CofO
|
JOHN COLEMAN
|
|
Green Building Final
|
1/26/2024
|
Approved
|
JOHN COLEMAN
|