10419 W ILONA AVE 90064

Certificate Information: 10419 W ILONA AVE 90064

Application / Permit
21014-10000-05694
Plan Check / Job No.
B21LA21364
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF (E) DETACHED 2-CAR GARGE WITH GROUND FLOOR ADDITION TO 1-CAR GARAGE WITH ADU PER LAMC 12.22 A33(c) AND (d)
Permit Issued
Issued on 4/26/2022
Issuing Office
Current Status
CofO Issued on 6/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 KHEDER ALRAZAA
Corrections Issued 12/23/2021 KHEDER ALRAZAA
Quality Review Completed 12/30/2021 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 2/18/2022 KHEDER ALRAZAA
Plan Check Approved 4/4/2022 KHEDER ALRAZAA
Issued 4/26/2022 APPLICANT
Building Plans Picked Up 4/28/2022 APPLICANT
CofO in Progress 6/8/2023 MICHAEL PELHAM
CofO in Progress 6/8/2023 MICHAEL PELHAM
Permit Finaled 6/9/2023 DANIEL ORRANTE
CofO Issued 6/9/2023 DANIEL ORRANTE
Permit Finaled 6/9/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/18/2022 JOSE HERNANDEZ
Miscellaneous Cleared 1/21/2022 RAYMOND MUGAMBWA
Eng Process Fee Ord 176,300 Cleared 1/25/2022 DINAH GARIN
Sewer availability Cleared 1/25/2022 DINAH GARIN
Specific Plan Cleared 2/2/2022 PEDRO AYALA
Roof/Waste drainage to street Cleared 3/15/2022 DINAH GARIN
Construction near power lines Cleared 3/22/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/12/2022 Corrections Issued EVAN COOPER
METHANE-Barrier 8/12/2022 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 8/12/2022 Not Ready for Inspection EVAN COOPER
Underground Mechanical 8/12/2022 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 8/18/2022 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Rough 11/7/2022 Corrections Issued MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 11/7/2022 Corrections Issued MICHAEL PELHAM
PLUMBING-Rough 11/7/2022 Corrections Issued MICHAEL PELHAM
Sewer 11/7/2022 Not Ready for Inspection MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 11/15/2022 Approved MICHAEL PELHAM
Footing/Foundation/Slab 11/15/2022 Approved MICHAEL PELHAM
METHANE-Barrier 11/15/2022 Approved MICHAEL PELHAM
METHANE-Final 11/15/2022 Approved MICHAEL PELHAM
METHANE-Rough 11/15/2022 Approved MICHAEL PELHAM
METHANE-Subgrade 11/15/2022 Approved MICHAEL PELHAM
PLUMBING-Rough 11/15/2022 Partial Approval MICHAEL PELHAM
Sewer 11/15/2022 Not Ready for Inspection MICHAEL PELHAM
Underground Mechanical 11/15/2022 Partial Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 12/9/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 12/9/2022 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 12/9/2022 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 12/9/2022 Corrections Issued STEPHANIE SWANSON
Insulation 12/15/2022 Corrections Issued MICHAEL PELHAM
BUILDING-Rough-Frame 12/23/2022 Approved STEPHANIE SWANSON
Drywall Nailing 12/23/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 12/23/2022 Approved STEPHANIE SWANSON
Green Building Rough 12/23/2022 Approved STEPHANIE SWANSON
Shower Pan 12/23/2022 Approved STEPHANIE SWANSON
Drywall Nailing 1/17/2023 Partial Approval STEPHANIE SWANSON
Interior/Exterior Lathing 1/17/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Final 3/14/2023 Not Ready for Inspection STEPHANIE SWANSON
ELECTRICAL-Final 4/4/2023 Partial Approval STEPHANIE SWANSON
Sewer 4/4/2023 Corrections Issued STEPHANIE SWANSON
Sewer 4/5/2023 Approved STEPHANIE SWANSON
Drywall Nailing 5/16/2023 Approved BRENDAN LOONEY
ELECTRICAL-Final 5/16/2023 Corrections Issued BRENDAN LOONEY
Final 5/16/2023 Corrections Issued BRENDAN LOONEY
Green Building Final 5/16/2023 Approved BRENDAN LOONEY
HVAC-Final 5/16/2023 Approved BRENDAN LOONEY
PLUMBING-Final 5/16/2023 Corrections Issued BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 5/16/2023 SGSOV Approved BRENDAN LOONEY
Smoke Detectors 5/16/2023 Approved BRENDAN LOONEY
Final 5/24/2023 OK to Issue CofO BRENDAN LOONEY