6525 W COLGATE AVE 90048

Certificate Information: 6525 W COLGATE AVE 90048

Application / Permit
21014-10000-05692
Plan Check / Job No.
B21LA21324
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan - (E) DETACHED GARAGE TO BE CONVERTED INTO ADU PER LAMC 12.22 A.33 (c)-(d) & TWO STORY GROUND FLOOR ADDITION.
Permit Issued
Issued on 2/16/2023
Issuing Office
Current Status
CofO Issued on 2/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 SERGIO GUTIERREZ
Corrections Issued 3/16/2022 SERGIO GUTIERREZ
Quality Review Completed 3/30/2022 FARUK SEZER
Applicant returned to address corrections 9/13/2022 SERGIO GUTIERREZ
Plan Check Approved 1/26/2023 SERGIO GUTIERREZ
Issued 2/16/2023 APPLICANT
CofO in Progress 2/15/2025 MICHAEL PELHAM
CofO in Progress 2/21/2025 DAVID FEILER
CofO in Progress 2/28/2025 DAVID FEILER
Permit Finaled 2/28/2025 RICHARD STEINBACH
CofO Issued 2/28/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 4/4/2022 JEANETTE VONG
Construction within easement Cleared 8/3/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 9/19/2022 JEANETTE VONG
Sewer availability Cleared 9/19/2022 JEANETTE VONG
Hydrant and Access approval Cleared 10/22/2022 RUEL COLE
Low Impact Development Cleared 10/31/2022 LUIS LUVANO
Roof/Waste drainage to street Cleared 11/1/2022 STEVE MELGAR

Contact Information

Contractor Goliath Construction; Lic. No.: 1056541-B       ,
Engineer Baich,, Brendon Chad; Lic. No.: C83347 PO BOX 8840      POMONA, CA 91701
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/23/2023 Approved JEREMY TODD
Excavation/Setback/Form/Re-Bar 3/2/2023 Not Ready for Inspection JEREMY TODD
Footing/Foundation/Slab 3/2/2023 Not Ready for Inspection JEREMY TODD
METHANE-Barrier 3/2/2023 Approved JEREMY TODD
METHANE-Subgrade 3/2/2023 Approved JEREMY TODD
Excavation/Setback/Form/Re-Bar 3/9/2023 Corrections Issued JEREMY TODD
Footing/Foundation/Slab 3/9/2023 Not Ready for Inspection JEREMY TODD
METHANE-Subgrade 2/16/2024 Approved MEL KHACHATOURIAN
PLUMBING-Rough 2/16/2024 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 2/20/2024 No Access for Inspection MEL KHACHATOURIAN
Underground Mechanical 2/20/2024 No Access for Inspection MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 2/22/2024 Approved MEL KHACHATOURIAN
Footing/Foundation/Slab 2/22/2024 Approved MEL KHACHATOURIAN
Deputy Wood Construction 3/12/2024 No Access for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 4/26/2024 Corrections Issued MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 5/2/2024 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Corrections Issued MEL KHACHATOURIAN
ELECTRICAL-Rough 5/8/2024 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 5/8/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 5/8/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 5/9/2024 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 5/9/2024 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 5/17/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 5/31/2024 Partial Approval MEL KHACHATOURIAN
Insulation 6/6/2024 Approved MEL KHACHATOURIAN
Drywall Nailing 6/13/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 6/13/2024 Approved MEL KHACHATOURIAN
Shower Pan 6/13/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 7/2/2024 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 10/9/2024 Approved MEL KHACHATOURIAN
ELECTRICAL-Final 10/9/2024 Approved MEL KHACHATOURIAN
Final 10/9/2024 Corrections Issued MEL KHACHATOURIAN
HVAC-Final 10/9/2024 Partial Approval MEL KHACHATOURIAN
METHANE-Final 10/9/2024 Approved MEL KHACHATOURIAN
METHANE-Rough 10/9/2024 Approved MEL KHACHATOURIAN
PLUMBING-Final 10/9/2024 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 10/9/2024 SGSOV Approved MEL KHACHATOURIAN
Service/Power Release 10/9/2024 Not Ready for Inspection MEL KHACHATOURIAN
Smoke Detectors 10/9/2024 Approved MEL KHACHATOURIAN
Final 2/14/2025 OK to Issue CofO MEL KHACHATOURIAN
Service/Power Release 2/14/2025 Approved MEL KHACHATOURIAN