6525 W COLGATE AVE 90048
Certificate Information: 6525 W COLGATE AVE 90048
- Application / Permit
- 21014-10000-05692
- Plan Check / Job No.
- B21LA21324
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan - (E) DETACHED GARAGE TO BE CONVERTED INTO ADU PER LAMC 12.22 A.33 (c)-(d) & TWO STORY GROUND FLOOR ADDITION.
- Permit Issued
- Issued on 2/16/2023
- Issuing Office
- Current Status
- CofO Issued on 2/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | SERGIO GUTIERREZ |
| Corrections Issued | 3/16/2022 | SERGIO GUTIERREZ |
| Quality Review Completed | 3/30/2022 | FARUK SEZER |
| Applicant returned to address corrections | 9/13/2022 | SERGIO GUTIERREZ |
| Plan Check Approved | 1/26/2023 | SERGIO GUTIERREZ |
| Issued | 2/16/2023 | APPLICANT |
| CofO in Progress | 2/15/2025 | MICHAEL PELHAM |
| CofO in Progress | 2/21/2025 | DAVID FEILER |
| CofO in Progress | 2/28/2025 | DAVID FEILER |
| Permit Finaled | 2/28/2025 | RICHARD STEINBACH |
| CofO Issued | 2/28/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 4/4/2022 | JEANETTE VONG |
| Construction within easement | Cleared | 8/3/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 9/19/2022 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 10/22/2022 | RUEL COLE |
| Low Impact Development | Cleared | 10/31/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 11/1/2022 | STEVE MELGAR |
Contact Information
| Contractor | Goliath Construction; Lic. No.: 1056541-B | , |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | PO BOX 8840 POMONA, CA 91701 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/23/2023 | Approved | JEREMY TODD |
| Excavation/Setback/Form/Re-Bar | 3/2/2023 | Not Ready for Inspection | JEREMY TODD |
| Footing/Foundation/Slab | 3/2/2023 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Barrier | 3/2/2023 | Approved | JEREMY TODD |
| METHANE-Subgrade | 3/2/2023 | Approved | JEREMY TODD |
| Excavation/Setback/Form/Re-Bar | 3/9/2023 | Corrections Issued | JEREMY TODD |
| Footing/Foundation/Slab | 3/9/2023 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Subgrade | 2/16/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 2/16/2024 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 2/20/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Underground Mechanical | 2/20/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 2/22/2024 | Approved | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 2/22/2024 | Approved | MEL KHACHATOURIAN |
| Deputy Wood Construction | 3/12/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2024 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2024 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/8/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 5/8/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/9/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 5/9/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 5/17/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/31/2024 | Partial Approval | MEL KHACHATOURIAN |
| Insulation | 6/6/2024 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 6/13/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 6/13/2024 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 6/13/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 7/2/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 10/9/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 10/9/2024 | Approved | MEL KHACHATOURIAN |
| Final | 10/9/2024 | Corrections Issued | MEL KHACHATOURIAN |
| HVAC-Final | 10/9/2024 | Partial Approval | MEL KHACHATOURIAN |
| METHANE-Final | 10/9/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 10/9/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 10/9/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 10/9/2024 | SGSOV Approved | MEL KHACHATOURIAN |
| Service/Power Release | 10/9/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Smoke Detectors | 10/9/2024 | Approved | MEL KHACHATOURIAN |
| Final | 2/14/2025 | OK to Issue CofO | MEL KHACHATOURIAN |
| Service/Power Release | 2/14/2025 | Approved | MEL KHACHATOURIAN |