3923 S COOLIDGE AVE 90066

Certificate Information: 3923 S COOLIDGE AVE 90066

Application / Permit
21014-10000-05691
Plan Check / Job No.
B21LA21299
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND ADDITION TO (E) SFD
Permit Issued
Issued on 1/10/2022
Issuing Office
Current Status
CofO Issued on 1/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 FERNANDO FLORES
Corrections Issued 11/19/2021 FERNANDO FLORES
Applicant returned to address corrections 12/14/2021 DANIEL SANJUAN
Applicant returned to address corrections 12/27/2021 ADAM HEGAZI
Plan Check Approved 1/4/2022 ADAM HEGAZI
Issued 1/10/2022 APPLICANT
Building Plans Picked Up 1/11/2022 APPLICANT
CofO in Progress 1/13/2023 JESUS RODRIGUEZ
Permit Finaled 1/17/2023 DANIEL ORRANTE
CofO Issued 1/17/2023 DANIEL ORRANTE
Permit Finaled 1/17/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/3/2021 TRACY TATE
Roof/Waste drainage to street Cleared 12/3/2021 TRACY TATE
Sewer availability Cleared 12/3/2021 TRACY TATE
Specific Plan Cleared 12/22/2021 VALERIA CEJA

Contact Information

Contractor 8a General Construction; Lic. No.: 1020625-B 11660 EL GRANADA AVE      LYNWOOD, CA 90262
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/18/2022 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 2/18/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 3/14/2022 Partial Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 3/16/2022 Partial Approval PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 3/16/2022 Not Ready for Inspection PATRICK QUALEY
Green Building Rough 3/16/2022 Not Ready for Inspection PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Partial Approval PATRICK QUALEY
Deputy Wood Construction 5/11/2022 No Access for Inspection PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 5/11/2022 Partial Approval PATRICK QUALEY
BUILDING-Rough-Frame 5/19/2022 Approved PATRICK QUALEY
ELECTRICAL-Rough 5/19/2022 Approved PATRICK QUALEY
Green Building Rough 5/19/2022 Approved PATRICK QUALEY
HVAC-Rough 5/19/2022 Corrections Issued PATRICK QUALEY
Interior/Exterior Lathing 5/19/2022 Partial Approval PATRICK QUALEY
PLUMBING-Rough 5/19/2022 Approved PATRICK QUALEY
Insulation 5/24/2022 Approved PATRICK QUALEY
Shower Pan 5/24/2022 Corrections Issued PATRICK QUALEY
Shower Pan 5/26/2022 Conditional Approval CLAYTON GRAHAM
Drywall Nailing 6/3/2022 Approved JESUS RODRIGUEZ
Gas Test 6/3/2022 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 6/3/2022 Approved JESUS RODRIGUEZ
Sewer 6/30/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 6/30/2022 Approved JESUS RODRIGUEZ
Final 11/15/2022 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 11/15/2022 Approved JESUS RODRIGUEZ
Green Building Final 11/15/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/15/2022 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 11/15/2022 Approved JESUS RODRIGUEZ
Final 12/12/2022 Not Ready for Inspection JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/12/2022 SGSOV Not Ready JESUS RODRIGUEZ
ELECTRICAL-Final 12/15/2022 Approved JESUS RODRIGUEZ
Final 12/15/2022 Corrections Issued JESUS RODRIGUEZ
Gas Test 12/15/2022 Approved JESUS RODRIGUEZ
HVAC-Final 12/15/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 12/15/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/15/2022 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 12/15/2022 Approved JESUS RODRIGUEZ
Final 1/13/2023 OK to Issue CofO JESUS RODRIGUEZ