436 E 105TH ST 90003
Certificate Information: 436 E 105TH ST 90003
- Application / Permit
- 21014-10000-05690
- Plan Check / Job No.
- B21LA21291
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO EXISTING DETACED GARAGE AND CONVERT TO A DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 7/11/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2021 | STANLEY RAAP |
| Corrections Issued | 11/23/2021 | STANLEY RAAP |
| Building Plans Picked Up | 1/14/2022 | APPLICANT |
| Plan Check Approved | 7/11/2023 | FERNANDO FLORES |
| Issued | 7/11/2023 | APPLICANT |
| CofO in Progress | 11/21/2024 | ANTHONY EGSON |
| CofO in Progress | 11/22/2024 | ANSON MAGLASANG |
| CofO in Progress | 11/22/2024 | ANTHONY EGSON |
| CofO Issued | 11/27/2024 | ANSON MAGLASANG |
| Permit Finaled | 11/27/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 2/26/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 3/30/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2023 | ABEL CASILLAS |
| Sewer availability | Cleared | 4/7/2023 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/28/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 10/5/2023 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 10/11/2023 | Partial Approval | JOHN KLARIN |
| Pre-Inspection | 10/19/2023 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 10/24/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 12/5/2023 | Partial Inspection | JOHN KLARIN |
| Green Building Rough | 12/5/2023 | Not Ready for Inspection | JOHN KLARIN |
| Sewer | 12/15/2023 | Approved | JOHN KLARIN |
| Insulation | 1/4/2024 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 2/15/2024 | Corrections Issued | BEN MOLSTAD |
| Insulation | 2/15/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 3/6/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 3/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 3/11/2024 | Approved | BEN MOLSTAD |
| Insulation | 3/11/2024 | Corrections Issued | BEN MOLSTAD |
| Insulation | 3/18/2024 | Conditional Approval | BEN MOLSTAD |
| Interior/Exterior Lathing | 4/2/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 4/8/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 4/24/2024 | Approved | BEN MOLSTAD |
| Green Building Rough | 4/24/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 6/20/2024 | Approved | BEN MOLSTAD |
| Final | 6/20/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Final | 6/20/2024 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 6/20/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 7/1/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Green Building Final | 7/1/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 7/1/2024 | SGSOV Not Ready | JAMES CHAVEZ |
| Smoke Detectors | 7/1/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Final | 7/3/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 7/3/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 7/3/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 7/3/2024 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 7/3/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 7/11/2024 | Corrections Issued | JAMES CHAVEZ |
| Green Building Final | 7/11/2024 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 7/11/2024 | SGSOV Not Ready | JAMES CHAVEZ |
| Smoke Detectors | 7/11/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 10/9/2024 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 10/9/2024 | SGSOV Not Ready | BARRY HACHE |
| Smoke Detectors | 10/9/2024 | Corrections Issued | BARRY HACHE |
| Final | 10/21/2024 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/21/2024 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 10/21/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 10/23/2024 | Approved | ANTHONY EGSON |
| Final | 10/28/2024 | Partial Approval | ANTHONY EGSON |
| HVAC-Final | 10/28/2024 | Approved | ANTHONY EGSON |
| Final | 11/20/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 11/20/2024 | Approved | ANTHONY EGSON |
| Final | 11/22/2024 | OK to Issue CofO | ANTHONY EGSON |