24702 S BROAD AVE 90744

Certificate Information: 24702 S BROAD AVE 90744

Application / Permit
21014-10000-05626
Plan Check / Job No.
B21LA21092
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ADU WITH AN ADDITION PER DETACHED ADU ORDINANCE (1-STORY) "COMPLY WITH DEPARTMENT ORDER effective date 10/28/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 3/8/2022
Issuing Office
Current Status
CofO Issued on 1/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2021 APPLICANT
Assigned to Plan Check Engineer 11/12/2021 CARLOS MONTES
Corrections Issued 11/12/2021 CARLOS MONTES
Applicant returned to address corrections 1/7/2022 CARLOS MONTES
Plan Check Approved 3/3/2022 CARLOS MONTES
Issued 3/8/2022 APPLICANT
CofO in Progress 11/4/2022 EUGENE CASSIDY
Permit Finaled 1/9/2023 ANSON MAGLASANG
CofO Issued 1/9/2023 ANSON MAGLASANG
Permit Finaled 1/9/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 11/16/2021 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 11/19/2021 JOSE HERNANDEZ
Sewer availability Cleared 11/19/2021 JOSE HERNANDEZ
Clean Up Green Up Cleared 11/22/2021 STEVEN WECHSLER
Low Impact Development Cleared 12/28/2021 CHRIS VONG
Roof/Waste drainage to street Cleared 12/28/2021 JOSE HERNANDEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Gosen,, James W; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342
Engineer Gosen,, James W; Lic. No.: NA43590       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/7/2022 Partial Approval EUGENE CASSIDY
Sewer 4/7/2022 Not Ready for Inspection EUGENE CASSIDY
Special/Order Compliance 4/7/2022 Corrections Issued EUGENE CASSIDY
Deputy Methane Barrier 4/25/2022 Approved JOHN KLARIN
Footing/Foundation/Slab 4/28/2022 Approved EUGENE CASSIDY
METHANE-Barrier 4/28/2022 Approved EUGENE CASSIDY
METHANE-Subgrade 4/28/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 4/28/2022 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 5/26/2022 Approved EUGENE CASSIDY
ELECTRICAL-Rough 5/26/2022 Approved EUGENE CASSIDY
Green Building Rough 5/26/2022 Approved EUGENE CASSIDY
HVAC-Rough 5/26/2022 Approved EUGENE CASSIDY
METHANE-Rough 5/26/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 5/26/2022 Approved EUGENE CASSIDY
Insulation 5/31/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 5/31/2022 Partial Approval EUGENE CASSIDY
Drywall Nailing 6/6/2022 Approved EUGENE CASSIDY
Sewer 7/12/2022 Approved EUGENE CASSIDY
Final 7/14/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 7/14/2022 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/14/2022 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 7/14/2022 Approved EUGENE CASSIDY
Final 7/28/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 7/28/2022 Not Ready for Inspection EUGENE CASSIDY
Final 8/8/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 8/8/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 10/28/2022 Approved EUGENE CASSIDY
Final 10/28/2022 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 10/28/2022 Approved EUGENE CASSIDY
PLUMBING-Final 10/28/2022 Approved EUGENE CASSIDY