244 E 53RD ST 90011
Certificate Information: 244 E 53RD ST 90011
- Application / Permit
- 21014-10000-05596
- Plan Check / Job No.
- B21LA20938
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (6) Church
- Work Description
- Remodel existing 1 story, Type VB, church add second story office and expand foot prints, restripe parking. sprinkler throughout.
- Permit Issued
- Issued on 2/21/2025
- Issuing Office
- Metro
- Current Status
- Issued on 2/21/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | KESETE HAREGOT |
| Disabled Access Plans Picked Up | 12/13/2021 | APPLICANT |
| Green Plans Picked Up | 12/14/2021 | APPLICANT |
| Corrections Issued | 12/16/2021 | KESETE HAREGOT |
| Quality Review Completed | 12/22/2021 | FARUK SEZER |
| Building Plans Picked Up | 12/28/2021 | APPLICANT |
| Applicant returned to address corrections | 4/18/2023 | KESETE HAREGOT |
| Applicant returned to address corrections | 10/1/2024 | KESETE HAREGOT |
| Applicant returned to address corrections | 10/9/2024 | KESETE HAREGOT |
| Applicant returned to address corrections | 10/30/2024 | KESETE HAREGOT |
| Plan Check Approved | 12/23/2024 | KESETE HAREGOT |
| Issued | 2/21/2025 | APPLICANT |
Permit Application Clearance Information
| DAS Clearance | Cleared | 12/16/2021 | KESETE HAREGOT |
| Address approval | Cleared | 3/14/2022 | TREVOR QUAN |
| Fire Marshal Fire Life Safety | Cleared | 10/30/2024 | WILLIAM JOHNS |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 11/4/2024 | TREVOR QUAN |
| "Q" conditions | Cleared | 11/7/2024 | MAYELA VILLA |
| Prkng lot landscape/Water mgmt | Cleared | 11/15/2024 | JASON CHAN |
| Green Code | Cleared | 11/19/2024 | AARON COSTA |
| Work Adjacent to Public Way | Cleared | 11/22/2024 | ALEXANDER PHAM |
| Low Impact Development | Cleared | 12/10/2024 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 12/16/2024 | DAVID LOPEZ |
Contact Information
| Architect | Mccooey,, Yumiko M; Lic. No.: C36551 | 15021 VENTURA BLVD #1041 SHERMAN OAKS, CA 91403 |
| Contractor | F & Constanza Construction Inc; Lic. No.: 1072351-B | 10561 PERRIN DRIVE GARDEN GROVE, CA 92840 |
| Engineer | Ibarra,, Marco A; Lic. No.: C74010 | 16 N MARENGON AVE STE 604 PASADENA, CA 91101 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/22/2025 | Approved | DARRYL ARNOLD |
| Pre-Inspection | 4/28/2025 | Corrections Issued | DARRYL ARNOLD |
| Pre-Inspection | 4/29/2025 | Corrections Issued | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 5/9/2025 | Partial Inspection | ALFREDO LOPEZ |
| Pre-Inspection | 5/14/2025 | Partial Approval | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 5/22/2025 | Partial Approval | ALFREDO LOPEZ |
| Deputy Drilled-In Anchors | 6/26/2025 | Partial Approval | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 7/1/2025 | Approved | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2025 | Partial Approval | ALFREDO LOPEZ |
| Green Building Rough | 8/19/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Pre-Inspection | 9/26/2025 | Partial Inspection | ALFREDO LOPEZ |
| Green Building Rough | 10/7/2025 | Approved | DARRYL ARNOLD |
| Wood Frame | 10/7/2025 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 11/26/2025 | Approved | ALFREDO LOPEZ |
| Pre-Inspection | 3/13/2026 | Corrections Issued | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/27/2026 | Partial Approval | ALFREDO LOPEZ |