111 N FULLER AVE 90036

Certificate Information: 111 N FULLER AVE 90036

Application / Permit
21014-10000-05582
Plan Check / Job No.
B21LA20893
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior/exterior remodel of (E) two-story Single-Family Dwelling. Scope of work to include removal of (E) covered patio (262 SF) and construction of (N) attached trellis (432 SF) to the rear of the existing dwelling.
Permit Issued
Issued on 3/16/2022
Issuing Office
Current Status
CofO Issued on 11/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2021 APPLICANT
Assigned to Plan Check Engineer 11/10/2021 FERNANDO FLORES
Corrections Issued 11/10/2021 FERNANDO FLORES
Applicant returned to address corrections 2/23/2022 RAHEL BEYENE
Issued 3/16/2022 APPLICANT
Building Plans Picked Up 3/22/2022 APPLICANT
CofO in Progress 10/25/2022 MICHAEL LEWIS
Permit Finaled 11/17/2022 DEROLD HAUFF
CofO Issued 11/17/2022 DEROLD HAUFF
Permit Finaled 11/17/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/30/2021 JEREMY CHOK
HPOZ Cleared 2/8/2022 DANIEL MATA
Roof/Waste drainage to street Cleared 2/16/2022 KHOUNG LE

Contact Information

Architect Ryder,, Derek Thomas; Lic. No.: C32847 4111 GLENALBYN DRIVE      LOS ANGELES, CA 90065
Contractor Home Front Build Inc; Lic. No.: 962293-B 715 CYPRESS AVE      LOS ANGELES, CA 90065
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/11/2022 Corrections Issued STUART CHAPMAN
METHANE-Barrier 4/11/2022 Approved STUART CHAPMAN
METHANE-Subgrade 4/11/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 4/15/2022 Partial Inspection JUSTIN CURTIS
Footing/Foundation/Slab 5/2/2022 Partial Approval ADAM ESCOTO
Footing/Foundation/Slab 6/10/2022 Approved RYAN SALAZAR
ELECTRICAL-Rough 6/17/2022 Approved ADAM ESCOTO
PLUMBING-Rough 6/17/2022 Approved ADAM ESCOTO
HVAC-Rough 6/21/2022 Approved ADAM ESCOTO
Insulation 6/22/2022 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Not Ready for Inspection ADAM ESCOTO
BUILDING-Rough-Frame 6/29/2022 Approved JOSEPH MCGARRY
METHANE-Rough 6/29/2022 Approved JOSEPH MCGARRY
Insulation 7/7/2022 Approved ADAM ESCOTO
Interior/Exterior Lathing 7/7/2022 Partial Approval ADAM ESCOTO
Shower Pan 7/7/2022 Approved ADAM ESCOTO
Drywall Nailing 7/11/2022 Partial Approval ADAM ESCOTO
Drywall Nailing 7/13/2022 Approved ADAM ESCOTO
Final 10/18/2022 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 10/18/2022 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 10/18/2022 Approved MICHAEL LEWIS
Final 10/24/2022 OK to Issue CofO MICHAEL LEWIS