11123 W KLING ST 91602

Certificate Information: 11123 W KLING ST 91602

Application / Permit
21014-10000-05572
Plan Check / Job No.
B21LA20844
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 284 SQFT ONE -CAR GARAGE ATTACHED TO SINGLE FAMILY DWELLING, NEW BATHROOM ADDITION OF 64 SQFT AND MINOR INTERIOR REMDEL (1 OF 2)
Permit Issued
Issued on 6/23/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2021 APPLICANT
Assigned to Plan Check Engineer 11/12/2021 DANIEL SANJUAN
Corrections Issued 11/13/2021 DANIEL SANJUAN
Applicant returned to address corrections 4/14/2022 SAMUEL GONZALEZ
Building Plans Picked Up 4/26/2022 APPLICANT
No Progress 6/13/2022 KHUONG TRUONG
Applicant returned to address corrections 6/13/2022 KHUONG TRUONG
Plan Check Approved 6/23/2022 MINA HABILI
Issued 6/23/2022 APPLICANT
CofO in Progress 4/25/2023 JACK KARGODORIAN
CofO Issued 4/26/2023 MICHAEL SMITH
Permit Finaled 4/26/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/14/2021 AMIR KASHFI
Low Impact Development Cleared 6/14/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/17/2022 ABDULLAH SADOZAI

Contact Information

Contractor R R Construction; Lic. No.: 608557-B 10425 SEABURY LANE      LOS ANGELES, CA 90077
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/7/2022 Corrections Issued JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 7/12/2022 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 7/26/2022 Partial Approval CALEB MEISTER
Footing/Foundation/Slab 8/22/2022 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/8/2022 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 9/22/2022 Approved MISAEL ESPARZA
HVAC-Rough 9/22/2022 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 9/22/2022 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 9/29/2022 Not Ready for Inspection CLAYTON GRAHAM
PLUMBING-Rough 9/29/2022 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 10/6/2022 Partial Approval DEANDRE HOFFMAN
MERV13>=Rough 10/6/2022 Approved DEANDRE HOFFMAN
Shower Pan 10/6/2022 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 10/19/2022 Approved JACK KARGODORIAN
Insulation 10/28/2022 Approved JACK KARGODORIAN
Drywall Nailing 11/4/2022 Approved JACK KARGODORIAN
ELECTRICAL-Final 2/2/2023 Approved JACK KARGODORIAN
HVAC-Final 2/2/2023 Approved JACK KARGODORIAN
PLUMBING-Final 2/2/2023 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 3/15/2023 Approved JACK KARGODORIAN
Final 3/15/2023 Not Ready for Inspection JACK KARGODORIAN
Footing/Foundation/Slab 3/15/2023 Approved JACK KARGODORIAN
Green Building Final 3/15/2023 Approved JACK KARGODORIAN
Green Building Rough 3/15/2023 Approved JACK KARGODORIAN
MERV13>=Final 3/15/2023 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 3/15/2023 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 3/15/2023 Approved JACK KARGODORIAN
Final 4/25/2023 OK to Issue CofO JACK KARGODORIAN