2003 W BAXTER ST 90039
Certificate Information: 2003 W BAXTER ST 90039
- Application / Permit
- 21014-10000-05569
- Plan Check / Job No.
- B21LA20839
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN CHECK* CONVERT (E) GARAGE (441 SF) TO ADU AND ADD (174 SF) PER CA GC 65852.2(e)(1)(B) AND LAMC 12.22 A.33 (c)-(d), (g).
- Permit Issued
- Issued on 2/23/2022
- Issuing Office
- Current Status
- CofO in Progress on 6/22/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2021 | VIVIAN LAO |
| Corrections Issued | 11/17/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 2/9/2022 | VIVIAN LAO |
| Plan Check Approved | 2/10/2022 | VIVIAN LAO |
| Issued | 2/23/2022 | APPLICANT |
| CofO in Progress | 6/22/2023 | STUART CHAPMAN |
| No Progress | 6/22/2024 | SCOTT FINNILA |
| CofO in Progress | 6/22/2024 | SCOTT FINNILA |
Permit Application Clearance Information
| Address approval | Cleared | 12/16/2021 | KHOUNG LE |
| Roof/Waste drainage to street | Cleared | 12/16/2021 | KHOUNG LE |
| Street Frontage | Cleared | 12/16/2021 | KHOUNG LE |
| Grading Pre-Inspection | Cleared | 1/13/2022 | ROBERT HUGHES |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | KHOUNG LE |
| Sewer availability | Cleared | 1/26/2022 | KHOUNG LE |
| GPI Written Notices | Cleared | 2/10/2022 | VIVIAN LAO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/13/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/13/2022 | Partial Approval | THOMAS LOGRASSO |
| Sewer | 12/16/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/30/2023 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 1/30/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 1/30/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 1/30/2023 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 1/30/2023 | Approved | THOMAS LOGRASSO |
| Special/Order Compliance | 1/30/2023 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/6/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 2/6/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 2/6/2023 | Partial Approval | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 2/6/2023 | Approved | THOMAS LOGRASSO |
| Shower Pan | 2/6/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 2/13/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 2/13/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 4/5/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 5/16/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
| Final | 5/25/2023 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 5/25/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 5/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 6/21/2023 | OK to Issue CofO | STUART CHAPMAN |
| Smoke Detectors | 6/21/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 6/22/2023 | Approved | STUART CHAPMAN |
| HVAC-Final | 6/22/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 6/22/2023 | Approved | STUART CHAPMAN |
| Special/Order Compliance | 3/18/2024 | Corrections Issued | THOMAS LOGRASSO |