1432 E 49TH ST 90011

Certificate Information: 1432 E 49TH ST 90011

Application / Permit
21014-10000-05563
Plan Check / Job No.
B21LA20816
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF FIRE DAMAGED HOUSE DWELLING AND 1 STORY ADDITION AT THE REAR WITH INTERIOR REMODEL TO CREATE 4TH BEDROOM AND EXTEND INTO (E) FRONT PORCH.
Permit Issued
Issued on 6/3/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2021 APPLICANT
Assigned to Plan Check Engineer 11/12/2021 DANIEL SANJUAN
Corrections Issued 11/16/2021 DANIEL SANJUAN
Applicant returned to address corrections 1/28/2022 LUKE GONZALES
Applicant returned to address corrections 3/24/2022 JOSEPH RAFOLS
Building Plans Picked Up 4/7/2022 APPLICANT
Plan Check Approved 5/27/2022 RICARDO RAMIREZ
Issued 6/3/2022 APPLICANT
CofO in Progress 12/14/2023 ALEJANDRO DE ARTOLA
CofO Issued 12/22/2023 DEROLD HAUFF
Permit Finaled 12/22/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/14/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 5/17/2022 JEANETTE VONG
Sewer availability Cleared 5/17/2022 JEANETTE VONG

Contact Information

Contractor Randle Construction; Lic. No.: 1002172-B 13838 ROPER AVENUE      NORWALK, CA 90650
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/5/2022 Partial Inspection ANTHONY EGSON
Deputy Drilled-In Anchors 9/21/2022 Conditional Approval SHAVONNE ESPINOZA
Footing/Foundation/Slab 9/26/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 10/28/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/17/2022 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Partial Approval JULIAN AMAYA
ELECTRICAL-Rough 12/8/2022 Corrections Issued CALEB MEISTER
PLUMBING-Rough 12/8/2022 Corrections Issued CALEB MEISTER
PLUMBING-Rough 1/6/2023 Approved BRENDAN MORELLI
Deputy Wood Construction 1/9/2023 Conditional Approval BRENDAN MORELLI
ELECTRICAL-Rough 1/23/2023 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Partial Approval BRENDAN MORELLI
Interior/Exterior Lathing 2/3/2023 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 2/9/2023 Approved BRENDAN MORELLI
HVAC-Rough 2/9/2023 Approved BRENDAN MORELLI
Insulation 3/6/2023 Approved JAMES CHAVEZ
Drywall Nailing 3/17/2023 Approved STUART CHAPMAN
Drywall Nailing 4/26/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 11/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 11/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/28/2023 Approved ALEJANDRO DE ARTOLA
Final 11/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 11/28/2023 Approved ALEJANDRO DE ARTOLA
Service/Power Release 11/28/2023 Approved ALEJANDRO DE ARTOLA
Green Building Final 12/8/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Final 12/8/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/12/2023 Approved ALEJANDRO DE ARTOLA
Final 12/12/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 12/12/2023 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/12/2023 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 12/12/2023 Approved ALEJANDRO DE ARTOLA
Final 12/13/2023 OK to Issue CofO ALEJANDRO DE ARTOLA
Gas Test 12/13/2023 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/13/2023 SGSOV Approved ALEJANDRO DE ARTOLA