10185 W ELKWOOD ST 91352
Certificate Information: 10185 W ELKWOOD ST 91352
- Application / Permit
- 21014-10000-05537
- Plan Check / Job No.
- B21LA20762
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Rear addition to existing 1-story SFD including a new master bedroom and bathroom, additional bedroom, remodel existing bath and kitchen. Fire sprinkler system is required thru-out the building.
- Permit Issued
- Issued on 5/31/2022
- Issuing Office
- Metro
- Current Status
- Issued on 5/31/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2021 | LUKE GONZALES |
| Corrections Issued | 11/10/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 1/11/2022 | ZAW HAN |
| Applicant returned to address corrections | 2/10/2022 | LUKE GONZALES |
| Building Plans Picked Up | 2/16/2022 | APPLICANT |
| Plan Check Approved | 5/23/2022 | MINA HABILI |
| Issued | 5/31/2022 | APPLICANT |
Permit Application Clearance Information
| Public Works-Highway Ded. | Cleared | 5/19/2022 | CARLOS AGUILERA |
| Public Works-Sewers | Cleared | 5/19/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 5/23/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 5/23/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/23/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Maginn Construction Co; Lic. No.: 951163-B | 318 PARSONS LANDING LONG BEACH, CA 90803 |
| Engineer | Jung,, Jason; Lic. No.: C80569 | 106 S SIERRA MADRE BLVD UNIT #2 PASADENA, CA 91107 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/5/2022 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 7/11/2022 | Approved | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 7/12/2022 | Conditional Approval | DAVID MATSON |
| PLUMBING-Rough | 7/25/2022 | Approved | DAVID ANDERSON |
| Wood Frame | 7/25/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2022 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/25/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 10/25/2022 | Approved | DAVID ANDERSON |
| Green Building Rough | 10/25/2022 | Approved | DAVID ANDERSON |
| HVAC-Rough | 10/25/2022 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 10/25/2022 | Approved | DAVID ANDERSON |
| Shower Pan | 10/25/2022 | Approved | DAVID ANDERSON |
| Insulation | 11/7/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 11/7/2022 | Approved | DAVID ANDERSON |
| Drywall Nailing | 11/14/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 11/14/2022 | Approved | DAVID ANDERSON |