7731 S BOEING AVE 90045
Certificate Information: 7731 S BOEING AVE 90045
- Application / Permit
- 21014-10000-05529
- Plan Check / Job No.
- B21LA20727
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND 1ST & 2ND FLOOR ADDTIONS TO (E) 1-STORY SFD (TOTAL RES. FLOOR AREA=3125 SF). NEW 2-CAR GARAGE 486 SF ATTACHED TO SFD.
- Permit Issued
- Issued on 5/27/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | CHUNG-WEN CHUANG |
| Corrections Issued | 12/21/2021 | CHUNG-WEN CHUANG |
| Quality Review Completed | 12/28/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/30/2021 | APPLICANT |
| Applicant returned to address corrections | 2/1/2022 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 2/7/2022 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 2/9/2022 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 3/17/2022 | CHUNG-WEN CHUANG |
| Plan Check Approved | 5/20/2022 | CHUNG-WEN CHUANG |
| Issued | 5/27/2022 | APPLICANT |
| CofO in Progress | 7/9/2024 | BOBBY KEY |
| Permit Finaled | 7/12/2024 | DANIEL ORRANTE |
| CofO Issued | 7/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/10/2022 | FREDDY GARCIA |
| Permit | Cleared | 1/14/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | DINAH GARIN |
| Sewer availability | Cleared | 1/19/2022 | DINAH GARIN |
| GPI Written Notices | Cleared | 3/17/2022 | CHUNG-WEN CHUANG |
| Grading Pre-Inspection | Cleared | 3/17/2022 | JONATHAN HOM |
| Low Impact Development | Cleared | 3/24/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 3/30/2022 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/6/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 10/6/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 10/6/2022 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 10/12/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 11/7/2022 | Conditional Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 11/10/2022 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2022 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 12/9/2022 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 1/24/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 5/12/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 5/12/2023 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 5/12/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 5/17/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 5/24/2023 | Conditional Approval | BOBBY KEY |
| HVAC-Rough | 5/24/2023 | Conditional Approval | BOBBY KEY |
| PLUMBING-Rough | 5/24/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 7/10/2023 | Approved | BOBBY KEY |
| Green Building Rough | 7/10/2023 | Approved | BOBBY KEY |
| Insulation | 7/10/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 7/10/2023 | Partial Approval | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 7/10/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 8/7/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/17/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 1/17/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 5/14/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 5/14/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 5/14/2024 | Corrections Issued | BOBBY KEY |
| Sewer | 5/14/2024 | Approved | BOBBY KEY |
| Smoke Detectors | 5/14/2024 | Approved | BOBBY KEY |
| Underground Mechanical | 5/14/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 6/12/2024 | Approved | BOBBY KEY |
| Final | 6/12/2024 | Corrections Issued | BOBBY KEY |
| Gas Test | 6/12/2024 | Approved | BOBBY KEY |
| Green Building Final | 6/12/2024 | Approved | BOBBY KEY |
| HVAC-Final | 6/12/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 6/12/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 6/12/2024 | Approved | BOBBY KEY |
| Final | 7/9/2024 | OK to Issue CofO | BOBBY KEY |
| Footing/Foundation/Slab | 7/9/2024 | Approved | BOBBY KEY |
| Structural Steel Frame | 7/9/2024 | Approved | BOBBY KEY |