1840 S FAIRFAX AVE 90019
Certificate Information: 1840 S FAIRFAX AVE 90019
- Application / Permit
- 21014-10000-05522
- Plan Check / Job No.
- B21LA20701
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground floor addition and completely remodel to (E) SFD
- Permit Issued
- Issued on 2/23/2022
- Issuing Office
- Current Status
- CofO Issued on 1/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | KHEDER ALRAZAA |
| Corrections Issued | 12/9/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 12/17/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/23/2021 | APPLICANT |
| Plan Check Approved | 2/23/2022 | KHEDER ALRAZAA |
| Issued | 2/23/2022 | APPLICANT |
| CofO in Progress | 1/3/2023 | JOSE AVILA |
| Permit Finaled | 1/7/2023 | DEROLD HAUFF |
| CofO Issued | 1/7/2023 | DEROLD HAUFF |
| Permit Finaled | 1/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 1/4/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 2/15/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gonzalez,, Jorge Alberto; Lic. No.: C88762 | 859 BUTTE ST MC FARLAND, CA 93250 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/3/2022 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 3/3/2022 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 3/3/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2022 | Partial Approval | JOSE AVILA |
| Green Building Rough | 3/24/2022 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 3/29/2022 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 4/6/2022 | Partial Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2022 | Approved | JOSE AVILA |
| HVAC-Rough | 4/25/2022 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 5/5/2022 | Not Ready for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Not Ready for Inspection | JOSE AVILA |
| Green Building Rough | 5/5/2022 | Not Ready for Inspection | JOSE AVILA |
| Deputy Drilled-In Anchors | 5/9/2022 | Conditional Approval | RUBEN SALAS |
| Deputy Wood Construction | 5/9/2022 | Conditional Approval | RUBEN SALAS |
| BUILDING-Rough-Frame | 5/16/2022 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 5/16/2022 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Approved | JOSE AVILA |
| Green Building Rough | 5/16/2022 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 5/23/2022 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 5/27/2022 | Corrections Issued | JOSE AVILA |
| Gas Test | 5/27/2022 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 5/27/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 5/27/2022 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 5/27/2022 | Corrections Issued | JOSE AVILA |
| Shower Pan | 5/27/2022 | Not Ready for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 6/1/2022 | Order to Comply Issued | JOSE AVILA |
| ELECTRICAL-Rough | 6/1/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 6/1/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 6/6/2022 | Partial Approval | JOSE AVILA |
| Green Building Rough | 6/6/2022 | Approved | JOSE AVILA |
| Insulation | 6/6/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 6/13/2022 | Approved | JOSE AVILA |
| Shower Pan | 7/12/2022 | Approved | JOSE AVILA |
| Service/Power Release | 7/20/2022 | Approved | JOSE AVILA |
| HVAC-Final | 9/1/2022 | Corrections Issued | JOSE AVILA |
| Gas Test | 9/2/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 9/9/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 9/9/2022 | Approved | JOSE AVILA |
| Final | 9/9/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 9/9/2022 | Approved | JOSE AVILA |
| HVAC-Final | 9/9/2022 | Approved | JOSE AVILA |
| PLUMBING-Final | 9/9/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 9/9/2022 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 9/9/2022 | Approved | JOSE AVILA |
| Final | 9/14/2022 | Corrections Issued | JOSE AVILA |
| Gas Test | 9/14/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 9/14/2022 | SGSOV Approved | JOSE AVILA |
| Final | 1/3/2023 | OK to Issue CofO | JOSE AVILA |