1840 S FAIRFAX AVE 90019

Certificate Information: 1840 S FAIRFAX AVE 90019

Application / Permit
21014-10000-05522
Plan Check / Job No.
B21LA20701
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Ground floor addition and completely remodel to (E) SFD
Permit Issued
Issued on 2/23/2022
Issuing Office
Current Status
CofO Issued on 1/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2021 APPLICANT
Assigned to Plan Check Engineer 12/2/2021 KHEDER ALRAZAA
Corrections Issued 12/9/2021 KHEDER ALRAZAA
Quality Review Completed 12/17/2021 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 12/23/2021 APPLICANT
Plan Check Approved 2/23/2022 KHEDER ALRAZAA
Issued 2/23/2022 APPLICANT
CofO in Progress 1/3/2023 JOSE AVILA
Permit Finaled 1/7/2023 DEROLD HAUFF
CofO Issued 1/7/2023 DEROLD HAUFF
Permit Finaled 1/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 1/4/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 2/15/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 2/15/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Gonzalez,, Jorge Alberto; Lic. No.: C88762 859 BUTTE ST      MC FARLAND, CA 93250

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/3/2022 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 3/3/2022 Approved JOSE AVILA
Footing/Foundation/Slab 3/3/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/24/2022 Partial Approval JOSE AVILA
Green Building Rough 3/24/2022 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 3/29/2022 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/30/2022 Approved JOSE AVILA
ELECTRICAL-Rough 4/6/2022 Partial Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Approved JOSE AVILA
HVAC-Rough 4/25/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 5/5/2022 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Not Ready for Inspection JOSE AVILA
Green Building Rough 5/5/2022 Not Ready for Inspection JOSE AVILA
Deputy Drilled-In Anchors 5/9/2022 Conditional Approval RUBEN SALAS
Deputy Wood Construction 5/9/2022 Conditional Approval RUBEN SALAS
BUILDING-Rough-Frame 5/16/2022 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 5/16/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Approved JOSE AVILA
Green Building Rough 5/16/2022 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 5/23/2022 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 5/27/2022 Corrections Issued JOSE AVILA
Gas Test 5/27/2022 Partial Approval JOSE AVILA
HVAC-Rough 5/27/2022 Approved JOSE AVILA
PLUMBING-Rough 5/27/2022 Corrections Issued JOSE AVILA
Service/Power Release 5/27/2022 Corrections Issued JOSE AVILA
Shower Pan 5/27/2022 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 6/1/2022 Order to Comply Issued JOSE AVILA
ELECTRICAL-Rough 6/1/2022 Approved JOSE AVILA
PLUMBING-Rough 6/1/2022 Approved JOSE AVILA
Drywall Nailing 6/6/2022 Partial Approval JOSE AVILA
Green Building Rough 6/6/2022 Approved JOSE AVILA
Insulation 6/6/2022 Approved JOSE AVILA
Drywall Nailing 6/13/2022 Approved JOSE AVILA
Shower Pan 7/12/2022 Approved JOSE AVILA
Service/Power Release 7/20/2022 Approved JOSE AVILA
HVAC-Final 9/1/2022 Corrections Issued JOSE AVILA
Gas Test 9/2/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 9/9/2022 Approved JOSE AVILA
ELECTRICAL-Final 9/9/2022 Approved JOSE AVILA
Final 9/9/2022 Corrections Issued JOSE AVILA
Green Building Final 9/9/2022 Approved JOSE AVILA
HVAC-Final 9/9/2022 Approved JOSE AVILA
PLUMBING-Final 9/9/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 9/9/2022 SGSOV Not Ready JOSE AVILA
Smoke Detectors 9/9/2022 Approved JOSE AVILA
Final 9/14/2022 Corrections Issued JOSE AVILA
Gas Test 9/14/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 9/14/2022 SGSOV Approved JOSE AVILA
Final 1/3/2023 OK to Issue CofO JOSE AVILA