4623 S GRAMERCY PL 90062

Certificate Information: 4623 S GRAMERCY PL 90062

Application / Permit
21014-10000-05514
Plan Check / Job No.
B21LA20670
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED RECREATION ROOM TO ADU WITH ADDITION PER LAMC 12.22 A.33(c) AND (d). DEMO ATTACHED CARPORT. "COMPLY WITH DEPARTMENT ORDER. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
Permit Issued
Issued on 11/10/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2021 APPLICANT
Assigned to Plan Check Engineer 12/2/2021 RICARDO RAMIREZ
Corrections Issued 12/3/2021 RICARDO RAMIREZ
Plan Check Approved 4/15/2022 RICARDO RAMIREZ
Building Plans Picked Up 4/19/2022 APPLICANT
Issued 11/10/2022 APPLICANT
CofO in Progress 9/13/2023 SABAS ALONSO
Permit Finaled 9/21/2023 DEROLD HAUFF
CofO Issued 9/21/2023 DEROLD HAUFF
Permit Finaled 9/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/12/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 1/12/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/1/2022 CELINA MORENO
Sewer availability Cleared 3/1/2022 CELINA MORENO
Construction near power lines Cleared 3/12/2022 TINA MIRANDA

Contact Information

Contractor Harlev Plumbing And Remodeling; Lic. No.: 1010138-B 17639 SHERMAN WAY #A-131      VAN NUYS, CA 91406

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/16/2022 Not Ready for Inspection SABAS ALONSO
Sewer 12/19/2022 Approved SABAS ALONSO
Underground Mechanical 12/19/2022 Partial Approval SABAS ALONSO
Deputy Drilled-In Anchors 12/23/2022 Approved SABAS ALONSO
Deputy Other (see comments) 12/23/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 12/23/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 2/9/2023 Not Ready for Inspection SABAS ALONSO
Green Building Rough 2/9/2023 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/16/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 3/16/2023 Corrections Issued SABAS ALONSO
Green Building Rough 3/16/2023 Corrections Issued SABAS ALONSO
HVAC-Rough 3/16/2023 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 3/16/2023 Partial Approval SABAS ALONSO
PLUMBING-Rough 3/16/2023 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 3/28/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 3/28/2023 Approved SABAS ALONSO
Green Building Rough 3/28/2023 Approved SABAS ALONSO
HVAC-Rough 3/28/2023 Approved SABAS ALONSO
PLUMBING-Rough 3/28/2023 Approved SABAS ALONSO
Insulation 4/3/2023 Approved SABAS ALONSO
Drywall Nailing 4/14/2023 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 4/17/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Drywall Nailing 4/19/2023 Approved SABAS ALONSO
Green Building Final 6/27/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/27/2023 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 6/27/2023 Approved SABAS ALONSO
Final 9/6/2023 Corrections Issued BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 9/6/2023 SGSOV Not Ready BRENDAN MORELLI
Service/Power Release 9/6/2023 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 9/11/2023 Approved SABAS ALONSO
Final 9/11/2023 Corrections Issued SABAS ALONSO
HVAC-Final 9/11/2023 Approved SABAS ALONSO
PLUMBING-Final 9/11/2023 Approved SABAS ALONSO
Final 9/12/2023 OK to Issue CofO SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/12/2023 SGSOV Approved SABAS ALONSO
Service/Power Release 9/12/2023 Approved SABAS ALONSO