1428 W 35TH ST 90018

Certificate Information: 1428 W 35TH ST 90018

Application / Permit
21014-10000-05508
Plan Check / Job No.
B21LA20630
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ATTACHED GARAGE TO ADU AND ADDITION CREATING [33' X 19'] ADU AT 1ST FLOOR. Per LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 5/3/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2021 APPLICANT
Assigned to Plan Check Engineer 11/8/2021 JESSE JIMENEZ
Corrections Issued 11/9/2021 JESSE JIMENEZ
Plan Check Approved 2/18/2022 KHUONG TRUONG
Building Plans Picked Up 2/25/2022 APPLICANT
Issued 5/3/2022 APPLICANT
CofO in Progress 3/26/2025 SABAS ALONSO
Permit Finaled 3/27/2025 DEROLD HAUFF
CofO Issued 3/27/2025 DEROLD HAUFF
Permit Finaled 3/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/19/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/19/2022 CINDY QI
Roof/Waste drainage to street Cleared 1/19/2022 CINDY QI
Sewer availability Cleared 1/19/2022 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/15/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 8/19/2022 Conditional Approval SABAS ALONSO
METHANE-Barrier 8/19/2022 Not Ready for Inspection SABAS ALONSO
METHANE-Subgrade 8/19/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 3/3/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/3/2023 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 3/3/2023 Corrections Issued SABAS ALONSO
PLUMBING-Rough 3/3/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 4/19/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/19/2023 Approved SABAS ALONSO
Green Building Rough 4/19/2023 Approved SABAS ALONSO
HVAC-Rough 4/19/2023 Approved SABAS ALONSO
METHANE-Rough 4/19/2023 Approved SABAS ALONSO
Insulation 5/3/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 5/3/2023 Partial Approval SABAS ALONSO
Final 10/26/2023 No Access for Inspection SABAS ALONSO
Footing/Foundation/Slab 10/26/2023 No Access for Inspection SABAS ALONSO
Green Building Final 10/26/2023 No Access for Inspection SABAS ALONSO
METHANE-Barrier 10/26/2023 No Access for Inspection SABAS ALONSO
METHANE-Subgrade 10/26/2023 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/26/2023 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 10/26/2023 No Access for Inspection SABAS ALONSO
Drywall Nailing 3/5/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 3/5/2025 Approved SABAS ALONSO
Shower Pan 3/5/2025 Approved SABAS ALONSO
Shower Pan 3/5/2025 No Access for Inspection BARRY HACHE
Final 3/11/2025 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 3/11/2025 Approved SABAS ALONSO
Green Building Final 3/11/2025 Approved SABAS ALONSO
METHANE-Barrier 3/11/2025 Approved SABAS ALONSO
METHANE-Subgrade 3/11/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 3/11/2025 SGSOV Approved SABAS ALONSO
Smoke Detectors 3/11/2025 Approved SABAS ALONSO
Final 3/18/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 3/25/2025 OK to Issue CofO SABAS ALONSO