418 W E ST 90744

Certificate Information: 418 W E ST 90744

Application / Permit
21014-10000-05506
Plan Check / Job No.
B21LA20628
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW STORAGE ATTACHED TO EXISTING GARAGE
Permit Issued
Issued on 7/15/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2021 APPLICANT
Assigned to Plan Check Engineer 11/3/2021 FERNANDO FLORES
Corrections Issued 11/3/2021 FERNANDO FLORES
Building Plans Picked Up 11/9/2021 APPLICANT
Plan Check Approved 7/15/2022 FERNANDO FLORES
Issued 7/15/2022 APPLICANT
CofO in Progress 7/26/2023 EUGENE CASSIDY
CofO Issued 7/26/2023 ANSON MAGLASANG
Permit Finaled 7/26/2023 ANSON MAGLASANG

Permit Application Clearance Information

ZA Case Cleared 11/19/2021 MAXFIELD VERMY
Roof/Waste drainage to street Cleared 11/22/2021 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 1/19/2022 JOSE HERNANDEZ
Construction near power lines Cleared 2/27/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/15/2022 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 8/19/2022 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 8/23/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/12/2022 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Partial Approval EUGENE CASSIDY
Green Building Rough 9/12/2022 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 9/12/2022 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 9/12/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 5/17/2023 Approved EUGENE CASSIDY
Drywall Nailing 5/24/2023 Approved EUGENE CASSIDY
Special/Order Compliance 5/24/2023 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 6/15/2023 Partial Approval EUGENE CASSIDY
Final 6/15/2023 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 6/15/2023 Approved EUGENE CASSIDY
Green Building Final 6/15/2023 Approved EUGENE CASSIDY
Green Building Rough 6/15/2023 Approved EUGENE CASSIDY
METHANE-Barrier 6/15/2023 Approved EUGENE CASSIDY
METHANE-Final 6/15/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 6/15/2023 Approved EUGENE CASSIDY
METHANE-Subgrade 6/15/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/15/2023 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 6/15/2023 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 6/23/2023 Approved EUGENE CASSIDY
Final 6/23/2023 Corrections Issued EUGENE CASSIDY
METHANE-Final 6/23/2023 Approved EUGENE CASSIDY
METHANE-Rough 6/23/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/23/2023 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 6/23/2023 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 6/30/2023 Approved EUGENE CASSIDY
Final 6/30/2023 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 6/30/2023 Approved EUGENE CASSIDY
PLUMBING-Final 6/30/2023 Approved EUGENE CASSIDY
Smoke Detectors 6/30/2023 Approved EUGENE CASSIDY