6025 S KENISTON AVE 90043

Certificate Information: 6025 S KENISTON AVE 90043

Application / Permit
21014-10000-05477
Plan Check / Job No.
B21LA20482
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) GARAGE CONVERSION W/ ADDTION INTO ACCESORY DWELLING UNIT
Permit Issued
Issued on 1/19/2022
Issuing Office
Current Status
CofO Issued on 11/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2021 APPLICANT
Assigned to Plan Check Engineer 11/2/2021 RAHEL BEYENE
Corrections Issued 11/2/2021 RAHEL BEYENE
Applicant returned to address corrections 12/7/2021 FERNANDO FLORES
Plan Check Approved 1/18/2022 FERNANDO FLORES
Issued 1/19/2022 APPLICANT
Building Plans Picked Up 1/25/2022 APPLICANT
CofO in Progress 10/11/2022 ENRIQUE MIRELES
Permit Finaled 11/2/2022 RONALD MYRICK
CofO Issued 11/2/2022 RONALD MYRICK
Permit Finaled 11/2/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 11/15/2021 AMAAN MALIK
Roof/Waste drainage to street Cleared 11/15/2021 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 11/18/2021 AMAAN MALIK
Sewer availability Cleared 11/18/2021 AMAAN MALIK
Grading Pre-Inspection Cleared 1/7/2022 ROBERT HUGHES

Contact Information

Contractor Sutton Home Improvement; Lic. No.: 830509-B 914 NORTH DWIGHT AVE      COMPTON, CA 90220

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/16/2022 Approved FREDDIE RIVERA
Deputy Drilled-In Anchors 2/17/2022 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 2/23/2022 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 2/23/2022 Not Ready for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 3/1/2022 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 3/1/2022 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 3/14/2022 Corrections Issued ENRIQUE MIRELES
Green Building Rough 3/14/2022 Not Ready for Inspection ENRIQUE MIRELES
Insulation 3/14/2022 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 3/24/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 4/12/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/25/2022 Corrections Issued LILIANA PORTILLO
Underground Mechanical 4/25/2022 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 5/5/2022 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 5/5/2022 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 5/13/2022 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 5/13/2022 Approved ENRIQUE MIRELES
Drywall Nailing 5/27/2022 Approved ENRIQUE MIRELES
Green Building Rough 5/27/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/23/2022 SGSOV No Gas ENRIQUE MIRELES
Insulation 8/26/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 9/23/2022 Approved ENRIQUE MIRELES
Final 9/23/2022 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 9/23/2022 Approved ENRIQUE MIRELES
Green Building Final 9/23/2022 Approved ENRIQUE MIRELES
Smoke Detectors 9/23/2022 Approved ENRIQUE MIRELES
Final 10/7/2022 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 10/7/2022 Approved ENRIQUE MIRELES