14291 W GAGER ST 91331
Certificate Information: 14291 W GAGER ST 91331
- Application / Permit
- 21014-10000-05469
- Plan Check / Job No.
- B21LA09931
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-CAR CARPOT ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 4/15/2022
- Issuing Office
- Current Status
- CofO Issued on 8/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | DANIEL YIP |
| Corrections Issued | 7/7/2021 | DANIEL YIP |
| Quality Review Completed | 7/14/2021 | JASON HEALEY |
| Building Plans Picked Up | 7/23/2021 | APPLICANT |
| Applicant returned to address corrections | 10/29/2021 | DANIEL YIP |
| Applicant returned to address corrections | 2/10/2022 | DANIEL YIP |
| Plan Check Approved | 4/8/2022 | DANIEL YIP |
| Issued | 4/15/2022 | APPLICANT |
| CofO in Progress | 8/15/2022 | MICHEL ABAJAN |
| Permit Finaled | 8/17/2022 | RONALD MYRICK |
| CofO Issued | 8/17/2022 | RONALD MYRICK |
| Permit Finaled | 8/17/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/25/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/25/2022 | Approved | MICHEL ABAJAN |
| Wood Frame | 5/18/2022 | Approved | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 5/19/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/27/2022 | Approved | MICHEL ABAJAN |
| Final | 5/27/2022 | Partial Inspection | MICHEL ABAJAN |
| Green Building Final | 5/27/2022 | Partial Inspection | MICHEL ABAJAN |
| Green Building Rough | 5/27/2022 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 5/27/2022 | Partial Inspection | MICHEL ABAJAN |
| Drywall Nailing | 7/27/2022 | Approved | MISAEL ESPARZA |
| Final | 7/27/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 7/27/2022 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 7/27/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/15/2022 | Approved | MICHEL ABAJAN |
| Final | 8/15/2022 | OK to Issue CofO | MICHEL ABAJAN |
| Smoke Detectors | 8/15/2022 | Approved | MICHEL ABAJAN |